Project 23CB0067
DPWH infrastructure contract
Contract ID:
23CB0067
Fingerprint:
b71ea1a8800246…febc855af5 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 8, 2023 (3 yrs 6 mo ago) · Target/actual end Jul 22, 2024
Description:
CONCRETING OF BANGAD, BRGY. STO. DOMINGO FMR, BRGY. STO. DOMINGO, ORION, BATAAN
Category:
Roads
Implementing office:
DPWH Bataan 2nd DEO · Region III
Contractor:
Contract amount:
₱14,925,000.00 (₱14.9M)
Funding source:
Outside Infra - GAA 2023 DA FMR
Budget year:
2023
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| b1490cd92124… | Apr 20, 2023 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BATAAN 2ND DEO | ₱14,475,783.65 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25C00006 | Jun 16, 2025 | CONVERGENCE & SPL. SUPP. PROG.-SUSTAINABLE INFRASTRUCTURE PROJS. ALLEVIATING GAPS (SIPAG)-ACCESS RDS. AND/OR BRS. FR. THE NAT'L. ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BLDGS./ FACILITIES-CONST. OF ROAD (PACKAGE 3), BRGY. LIYANG, PILAR BRGY. BILOLO, ORIO | On-Going | ₱94.8M |
| 25CB0101 | Jun 16, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY WAKAS, ORION, BATAAN | Completed | ₱5.9M |
| 25CB0109 | Jun 16, 2025 | REHABILITATION OF MULTI-PURPOSE BUILDING (COVERED COURT) IN BARANGAY BALAGTAS, ORION, BATAAN | On-Going | ₱4.8M |
| 25CB0115 | May 28, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - RAINWATER COLLECTOR SYSTEM, BATAAN 2ND DISTRICT | Completed | ₱2.6M |
| 24CB0134 | May 27, 2025 | CONSTRUCTION OF 1-STOREY 3-CLASSROOM SCHOOL BUILDING, STO. DOMINGO ELEMENTARY SCHOOL, BARANGAY SANTO DOMINGO, ORION, BATAAN | Completed | ₱14.6M |
| 25CB0084 | May 27, 2025 | CONSTRUCTION (COMPLETION) OF NEW MUNICIPAL HALL, BARANGAY SAN VICENTE, ORION, BATAAN | On-Going | ₱9.7M |
| 25CB0085 | May 27, 2025 | REHABILITATION/COMPLETION OF MULTI-PURPOSE BUILDING IN BARANGAY WAWA (COVERED COURT), ORION, BATAAN | Completed | ₱3.5M |
| 25CB0089 | Apr 10, 2025 | CONSTRUCTION OF SEA WALL AT BARANGAY BANTAN, ORION, BATAAN | On-Going | ₱19.4M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.