Project 23CC0095

DPWH infrastructure contract
Contract ID:
23CC0095
Fingerprint:
0ce09d20d444a9…1cd8cdf2a0 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 13, 2023 (3 yrs 9 mo ago) · Target/actual end Jan 8, 2024
Description:
REHABILITATION OF WATERWAYS AND CONSTRUCTION OF WATER PUMPING STATION AT BARANGAY MALIS, GUIGUINTO, BULACAN
Category:
Flood Control and Drainage
Implementing office:
DPWH Bulacan 1st DEO · Region III
Contractor:
L.R. TIQUI BUILDERS, INC. · DPWH contractor code 13810
Contract amount:
₱77,682,237.38 (₱77.7M)
Funding source:
Regular Infra - GAA 2023 OO-2
Budget year:
2023

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
f323eb7ad935…Feb 1, 2023DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BULACAN 1ST DEO₱74,574,802.33

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25C00491Jun 22, 2025NETWORK DEVELOPMENT PROGRAM-OFF-CARRIAGEWAY IMPROVEMENT-PRIMARY ROADS-MAHARLIKA HIGHWAY, PROVINCE OF BULACANOn-Going₱12.5M
25CC0280May 23, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. TIAONG, GUIGUINTO, BULACANOn-Going₱4.8M
25CC0303May 23, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY SANTA CRUZ, GUIGUINTO, BULACANOn-Going₱19.3M
25CC0413May 23, 2025CONSTRUCTION OF ROAD INCLUDING DRAINAGE STRUCTURE, BARANGAY TABANG, GUIGUINTO, BULACANOn-Going₱4.9M
25CC0455May 23, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING TABANG ELEMENTARY SCHOOL, BARANGAY TABANG, GUIGUINTO, BULACANOn-Going₱47.8M
25CC0509May 23, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (GUIGUINTO OVAL SPORTS COMPLEX) POBLACION, GUIGUINTO, BULACANOn-Going₱19.3M
24CC0669Mar 27, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT BARANGAY MALIS (PUROK 4 TO PUROK 5), GUIGUINTO, BULACANOn-Going₱74.1M
25CC0325Mar 21, 2025CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE (PACKAGE A) AT BARANGAY SANTA CRUZ (PUROK 5), GUIGUINTO, BULACANOn-Going₱74.1M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.