DPWH infrastructure contract
Contract ID:
23CC0181
Fingerprint:
c93915cae2d219…8adf277741 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 27, 2023 (3 yrs 7 mo ago) · Target/actual end Nov 21, 2023
Description:
CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BRGY. SAN ROQUE, HAGONOY, BULACAN
Category:
Flood Control and Drainage
Implementing office:
DPWH Bulacan 1st DEO · Region III
Contractor:
RVR3 CONSTRUCTION SUPPLY & SERVICES · DPWH contractor code 46817
As listed: RVR3 CONSTRUCTION SUPPLY AND SERVICES
Contract amount:
₱52,469,994.43 (₱52.5M)
Funding source:
Regular Infra - GAA 2023 CSSP
Budget year:
2023

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
df1bbfa7489b…Mar 20, 2023DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BULACAN 1ST DEO₱50,326,552.19

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25CC0352May 23, 2025REHABILITATION OF ROAD AT BARANGAY SAN AGUSTIN, HAGONOY, BULACANOn-Going₱9.6M
25CC0480May 23, 2025COMPLETION OF MULTI-PURPOSE BUILDING, BARANGAY SAN NICOLAS, HAGONOY, BULACANOn-Going₱14.5M
25CC0516May 23, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, EUGENIO G. SY TAMCO ELEMENTARY SCHOOL, HAGONOY, BULACANOn-Going₱14.5M
25CC0538May 23, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY SAN SEBASTIAN, HAGONOY, BULACANOn-Going₱18.4M
25CC0312Mar 27, 2025CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE AT BARANGAY SAN AGUSTIN (PARONG PARONG), HAGONOY, BULACANOn-Going₱69.3M
25CC0451Mar 27, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE (CHECK GATE), BARANGAY TAMPOK, AND BARANGAY SANTA MONICA, HAGONOY, BULACANOn-Going₱19.1M
25CC0212Mar 21, 2025REHABILITATION OF ROAD AT BARANGAY SAN NICOLAS, HAGONOY, BULACANOn-Going₱14.3M
25CC0227Mar 21, 2025REHABILITATION OF ROAD AT BARANGAY ABULALAS, HAGONOY, BULACANOn-Going₱14.4M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.