Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 23CC0490

DPWH infrastructure contract
Contract ID:
23CC0490
Fingerprint:
fc225027aea335…5176a1a70b Verified
Status:
On-Going
Physical progress:
69.4%
Timeline:
Start Nov 14, 2023 (3 yrs ago)
Description:
CONSTRUCTION OF BALAGTAS RIVER FLOOD MITIGATION STRUCTURE (STA. 14+124 TO STA. 14+274) AT BRGY. SAN JUAN, BALAGTAS, BULACAN
Category:
Flood Control and Drainage
Implementing office:
DPWH Bulacan 1st DEO · Region III
Contractor:
A.R.L. CONSTRUCTION · DPWH contractor code 27645
Contract amount:
₱69,480,238.81 (₱69.5M)
Funding source:
Outside Infra - Unprogrammed Appropriations 2023
Budget year:
2023

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25C00499Jun 16, 2025BRIDGE PROGRAM-RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES-UGONG BRIDGE (BO1987LZ) ALONG MANILA NORTH ROAD, PROVINCE OF BULACANCompleted₱16.2M
25CC0385May 23, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (TRAINING CENTER), HAGONOY, BULACANOn-Going₱19.3M
25CC0406May 23, 2025REHABILITATION OF UGONG CREEK (LEFT SIDE) BALAGTAS, BULACAN (PACKAGE G)On-Going₱95.0M
25CC0490May 23, 2025CONSTRUCTION OF REINFORCED CONCRETE RIVER PROTECTION ALONG BALAGTAS RIVER, BARANGAY SAN JUAN, PUROK 1, BALAGTAS, BULACAN (PACKAGE D)On-Going₱95.0M
25C00473Apr 8, 2025ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-PRIMARY ROADS-MANILA NORTH ROAD, PROVINCE OF BULACANOn-Going₱135.1M
25CC0433Apr 8, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, PLAZA BIGAA, BARANGAY BOROL 1ST, BALAGTAS, BULACANOn-Going₱14.5M
25CC0200Mar 21, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY HALL, BARANGAY BOROL 2ND, BALAGTAS, BULACANOn-Going₱4.9M
25CC0236Mar 21, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY SAN JUAN, BALAGTAS, BULACANOn-Going₱14.5M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.