Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 23CC0508

DPWH infrastructure contract
Contract ID:
23CC0508
Fingerprint:
241c6011fc17a1…747ef18c68 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Nov 29, 2023 (2 yrs 11 mo ago) · Target/actual end Mar 19, 2024
Description:
CONSTRUCTION (IMPROVEMENT) OF SLOPE PROTECTION STRUCTURE AND WATERWAYS AT BRGY. SANTO CRISTO, PULILAN, BULACAN
Category:
Unprogrammed Appropriations 2023
Implementing office:
DPWH Bulacan 1st DEO · Region III
Contract amount:
₱48,236,418.43 (₱48.2M)
Funding source:
Outside Infra - Unprogrammed Appropriations 2023
Budget year:
2023

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25CC0545Jun 11, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING BARANGAY BULIHAN, PLARIDEL, BULACANOn-Going₱14.5M
25CC0465May 23, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY SIPAT, PLARIDEL, BULACANOn-Going₱14.5M
25CC0532May 23, 2025CONSTRUCTION OF MULTI- PURPOSE BUILDING BARANGAY SAN JOSE, PLARIDEL, BULACANOn-Going₱14.5M
25C00493Apr 14, 2025ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-PRIMARY ROADS-MAHARLIKA HIGHWAY, PROVINCE OF BULACANOn-Going₱114.0M
25CC0300Apr 8, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE, PUROK 3, BARANGAY BULIHAN, PLARIDEL, BULACANOn-Going₱92.6M
25CC0301Apr 8, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE, PUROK 1, BARANGAY BAGONG SILANG, PLARIDEL, BULACANOn-Going₱92.8M
25CC0081Feb 25, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PAMPANGA RIVER AT BARANGAY SANTA LUCIA (PUROK 5 TO PUROK 6), CALUMPIT, BULACANOn-Going₱82.0M
25CC0090Feb 25, 2025CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE AT BARANGAY BAGBAGUIN (PUROK 5), PANDI, BULACANOn-Going₱74.1M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.