Project 23CC0556

DPWH infrastructure contract
Contract ID:
23CC0556
Fingerprint:
8532435fda27a3…4c2e55263a Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Dec 21, 2023 (2 yrs 10 mo ago) · Target/actual end Jul 1, 2024
Description:
CONSTRUCTION OF RIVER CONTROL SYSTEM AND REHABILITATION OF WATERWAYS ALONG GUIGUINTO RIVER BRGY. MALIS GUIGUINTO, BULACAN (STA. 05+067 TO STA. 05+267)
Category:
Flood Control and Drainage
Implementing office:
DPWH Bulacan 1st DEO · Region III
Contractor:
M3 KONSTRACT CORPORATION · DPWH contractor code 20201
As listed: M3 KONSTRACT CORPORATION (FORMERLY:MARGARITA CONSTRUCTION)
Contract amount:
₱48,247,315.97 (₱48.2M)
Funding source:
Outside Infra - Unprogrammed Appropriations 2023
Budget year:
2023

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
edd3188cf8aa…Dec 20, 2023DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BULACAN 1ST DEO₱46,315,097.44

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25C00491Jun 22, 2025NETWORK DEVELOPMENT PROGRAM-OFF-CARRIAGEWAY IMPROVEMENT-PRIMARY ROADS-MAHARLIKA HIGHWAY, PROVINCE OF BULACANOn-Going₱12.5M
25CC0280May 23, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. TIAONG, GUIGUINTO, BULACANOn-Going₱4.8M
25CC0303May 23, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY SANTA CRUZ, GUIGUINTO, BULACANOn-Going₱19.3M
25CC0413May 23, 2025CONSTRUCTION OF ROAD INCLUDING DRAINAGE STRUCTURE, BARANGAY TABANG, GUIGUINTO, BULACANOn-Going₱4.9M
25CC0455May 23, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING TABANG ELEMENTARY SCHOOL, BARANGAY TABANG, GUIGUINTO, BULACANOn-Going₱47.8M
25CC0509May 23, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (GUIGUINTO OVAL SPORTS COMPLEX) POBLACION, GUIGUINTO, BULACANOn-Going₱19.3M
24CC0669Mar 27, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT BARANGAY MALIS (PUROK 4 TO PUROK 5), GUIGUINTO, BULACANOn-Going₱74.1M
25CC0325Mar 21, 2025CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE (PACKAGE A) AT BARANGAY SANTA CRUZ (PUROK 5), GUIGUINTO, BULACANOn-Going₱74.1M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.