Project 23CE0065
DPWH infrastructure contract
Contract ID:
23CE0065
Fingerprint:
112d45c562d3c3…97684b8886 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 23, 2023 (3 yrs 8 mo ago) · Target/actual end Aug 21, 2023
Description:
CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY LINAO, LICAB, NUEVA ECIJA
Category:
Buildings and Facilities
Implementing office:
DPWH Nueva Ecija 1st DEO · Region III
Contractor:
M.M. SERRANO CONSTRUCTION COMPANY · DPWH contractor code 38549
Contract amount:
₱3,918,303.78 (₱3.9M)
Funding source:
Regular Infra - GAA 2023 CSSP
Budget year:
2023
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| e643e4d034f9… | Feb 9, 2023 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - NUEVA ECIJA 1ST DE | ₱3,918,303.78 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CE0295 | Jun 2, 2025 | CONSTRUCTION OF ROAD, BARANGAY SAN JOSE, LICAB, NUEVA ECIJA | Completed | ₱4.9M |
| 25CE0235 | Apr 2, 2025 | NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, LICAB-VICTORIA RD, NUEVA ECIJA | Completed | ₱33.9M |
| 25CE0265 | Apr 2, 2025 | CONSTRUCTION OF ROAD, BARANGAY SANTA MARIA, LICAB, NUEVA ECIJA | Completed | ₱4.9M |
| 25CE0105 | Mar 21, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG TALAVERA RIVER, BARANGAY SANTA LUCIA OLD, ZARAGOZA, NUEVA ECIJA | Completed | ₱48.5M |
| 25CE0019 | Feb 14, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY CAINGIN TABING ILOG, GUIMBA, NUEVA ECIJA | Completed | ₱3.0M |
| 25CE0065 | Feb 14, 2025 | REHABILITATION OF ROAD, BARANGAY POBLACION SUR, LICAB, NUEVA ECIJA | Completed | ₱10.7M |
| 25CE0072 | Feb 14, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG LABONG RIVER, BARANGAY SAN JUAN, LICAB, NUEVA ECIJA | Completed | ₱48.5M |
| 24CE0189 | Jul 3, 2024 | NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, TALAVERA - LICAB DIVERSION ROAD, NUEVA ECIJA | Completed | ₱19.4M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.