Project 23CE0216
DPWH infrastructure contract
Contract ID:
23CE0216
Fingerprint:
03cfddd17cfe60…6cf9d7d672 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Oct 12, 2023 (3 yrs 1 mo ago) · Target/actual end Dec 2, 2024
Description:
CONSTRUCTION OF SOLAR WATER SYSTEM, BARANGAY SAN MIGUEL, GUIMBA, NUEVA ECIJA
Category:
Water Provision and Storage
Implementing office:
DPWH Nueva Ecija 1st DEO · Region III
Contractor:
VILLAR GENERAL CONSTRUCTION & SUPPLIES · DPWH contractor code 22540
As listed: VILLAR GENERAL CONSTRUCTION AND SUPPLIES
Contract amount:
₱9,697,962.41 (₱9.7M)
Funding source:
Regular Infra - GAA 2023 CSSP
Budget year:
2023
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 07d31a8786c3… | Sep 27, 2023 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - NUEVA ECIJA 1ST DE | ₱9,697,962.41 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 24CE0362 | Jun 9, 2025 | CONSTRUCTION OF BRIDGE, BARANGAY CAVITE TO BARANGAY STA. ANA, GUIMBA, NUEVA ECIJA | Completed | ₱104.4M |
| 24CE0363 | Jun 9, 2025 | CONSTRUCTION OF BRIDGE, BARANGAY BALBALINO, GUIMBA, NUEVA ECIJA | Completed | ₱83.7M |
| 25CE0287 | Jun 9, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. BALBALINO, GUIMBA, NUEVA ECIJA | Completed | ₱5.1M |
| 25CE0323 | Jun 9, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. SAN ROQUE, GUIMBA, NUEVA ECIJA | Completed | ₱3.9M |
| 25CE0324 | Jun 9, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. ST. JOHN, GUIMBA, NUEVA ECIJA | Completed | ₱4.9M |
| 25CE0298 | Jun 2, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. BACAYAO, GUIMBA, NUEVA ECIJA | Completed | ₱3.9M |
| 25CE0299 | Jun 2, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. CABARUAN, GUIMBA, NUEVA ECIJA | Completed | ₱3.9M |
| 25CE0300 | Jun 2, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. MACATCATUIT, NUEVA ECIJA | Completed | ₱3.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.