Project 23CG0284

DPWH infrastructure contract
Contract ID:
23CG0284
Fingerprint:
dac85dc0c94d96…e07a47d099 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Oct 2, 2023 (3 yrs 1 mo ago) · Target/actual end Feb 28, 2024
Description:
CONSTRUCTION OF ONE (1) STOREY-TWO (2) CLASSROOM SCHOOL BUILDING AT MASANTOL HS (STA. LUCIA NHS, MASANTOL), MASANTOL, PAMPANGA
Category:
Buildings and Facilities
Implementing office:
DPWH Pampanga 1st DEO · Region III
Contractor:
EDDMARI CONSTRUCTION & TRADING · DPWH contractor code 20301
Contract amount:
₱5,699,925.15 (₱5.7M)
Funding source:
Outside Infra - GAA 2023 DepEd BEFF
Budget year:
2023

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
cb2f95c69b64…Sep 25, 2023DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - PAMPANGA 1ST DEO₱5,699,925.15

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25CG0117Jun 11, 2025BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD WITH SLOPE PROTECTION WORKS, BARANGAY CAMBASI (CENTRO), MASANTOL, PAMPANGACompleted₱56.3M
25CG0126Jun 11, 2025BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD WITH SLOPE PROTECTION WORKS, BARANGAY SAGRADA - BARANGAY NIGUI, MASANTOL, PAMPANGACompleted₱93.8M
25CG0127Jun 11, 2025BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD WITH SLOPE PROTECTION WORKS, BARANGAY BAGANG - BARANGAY BALIBAGO, MASANTOL, PAMPANGACompleted₱93.9M
25CG0086Jun 10, 2025BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION (COMPLETION) OF ROAD WITH SLOPE PROTECTION WORKS, BARANGAY ANAC - STA. LUCIA WAKAS, MASANTOL, PACompleted₱37.5M
25CG0170Jun 5, 2025CONCRETING OF SITIO MINDANAO, BRGY. ESTEBAN FARM-TO-MARKET ROAD, BRGY. ESTEBAN, MACABEBE, PAMPANGACompleted₱14.1M
25CG0014May 22, 2025FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - REHABILITATION OF ERODED PAMPANGA RIVER BANK AT BARANGAY BEBE ANAC, MASANTOL, PAMPANGAOn-Going₱140.4M
25CG0023May 22, 2025SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS) - CONSTRUCTION OF BY-PASS ROAD AND BRIDGE (SAN ESTEBAN) MACABEBE - MALAULI (PHASE IV), MASANTOL, PAMPANCompleted₱44.0M
25CG0111Apr 2, 2025SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REPAIR / REHABILITATION OF ERODED PAMPANGA RIVER BANK (LANDSLIDE SECTION) (PHASE 1)Terminated₱0

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.