Project 23CH0004

DPWH infrastructure contract
Contract ID:
23CH0004
Fingerprint:
322c624f214ed9…d523ee9813 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 27, 2023 (3 yrs 8 mo ago) · Target/actual end Jun 7, 2023
Description:
FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURE AND DRAINAGE SYSTEMS - CONSTRUCTION OF CONCRETE SLOPE PROTECTION ALONG DALAN BAPOR SANTA MONICA, SASMUAN, PAMPANGA
Category:
Flood Control and Drainage
Implementing office:
DPWH Pampanga 2nd DEO · Region III
Contractor:
R.M. VITUG CONSTRUCTION · DPWH contractor code 9227
Contract amount:
₱29,392,979.38 (₱29.4M)
Funding source:
Regular Infra - GAA 2023 OO-2
Budget year:
2023

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
a6c8f6868b00…Feb 7, 2023DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - PAMPANGA 2ND DEO₱28,656,104.16

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25CH0039Apr 3, 2025CONSTRUCTION OF SLOPE PROTECTION STRUCTURE, BARANGAY SAN PEDRO, SASMUAN, PAMPANGA, PHASE 1, SASMUAN, PAMPANGACompleted₱29.7M
25CH0024Feb 24, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT SANTA MONICA, SASMUAN, PAMPANGACompleted₱29.4M
25CH0030Feb 24, 2025CONSTRUCTION OF SLOPE PROTECTION STRUCTURE, BARANGAY BATANG 2ND, SASMUAN, PAMPANGACompleted₱29.7M
25CH0031Feb 24, 2025CONSTRUCTION OF SLOPE PROTECTION STRUCTURE, BARANGAY BATANG 2ND, SASMUAN, PAMPANGA, PHASE 2, SASMUAN, PAMPANGACompleted₱29.4M
25CH0032Feb 24, 2025CONSTRUCTION OF SLOPE PROTECTION STRUCTURE BARANGAY SABITANAN, SASMUAN, PAMPANGAOn-Going₱29.4M
24CH0122Jun 13, 2024CONSTRUCTION OF MULTI-PURPOSE BUILDING BARANGAY STA. MONICA, SASMUAN, PAMPANGACompleted₱4.9M
23CH0078Jun 14, 2023CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SAN PEDRO, SASMUAN, PAMPANGACompleted₱4.9M
23CH0062Apr 24, 2023REHABILITATION OF SLOPE PROTECTION ALONG UPPER DALAN BAPOR, PHASE II, AT SASMUAN, PAMPANGACompleted₱96.5M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.