Project 23CL0003
DPWH infrastructure contract
Contract ID:
23CL0003
Fingerprint:
ccd213da7de6d7…52950e8ba7 Verified
Status:
On-Going
Physical progress:
98.7%
Timeline:
Start Mar 28, 2023 (3 yrs 7 mo ago)
Description:
ROAD WIDENING-SECONDARY ROADS, OLONGAPO-BUGALLON RD - K0158 + 640 - K0161 + 000 , SAN NARCISO, ZAMBALES
Category:
Roads
Implementing office:
DPWH Zambales 1st DEO · Region III
Contractor:
R.A. PAHATI CONST. & SUPPLY, INC · DPWH contractor code 35843
As listed: R.A. PAHATI CONST. & SUPPLY, INC.
Contract amount:
₱69,218,739.08 (₱69.2M)
Funding source:
Regular Infra - GAA 2023 OO-1
Budget year:
2023
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 679934363b34… | Mar 21, 2023 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ZAMBALES 1ST DEO | ₱69,218,739.08 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CL0256 | Jul 18, 2025 | CONSTRUCTION OF FLOOD CONTROL RIVERBANK STRUCTURE ALONG SANTO TOMAS RIVER (OMAYA-BALINGCAGUING-PAITE SECTION), SAN NARCISO, ZAMBALES (PHASE 1) | On-Going | ₱48.8M |
| 25CL0257 | Jul 18, 2025 | CONSTRUCTION OF FLOOD CONTROL RIVERBANK STRUCTURE ALONG SANTO TOMAS RIVER (OMAYA-BALINGCAGUING-PAITE SECTION), SAN NARCISO, ZAMBALES (PHASE 2) | On-Going | ₱48.8M |
| 25CL0135 | Jun 6, 2025 | CONSTRUCTION OF ROAD, PUROK 1, BARANGAY DALLIPAWEN, SAN NARCISO, ZAMBALES | On-Going | ₱19.4M |
| 25CL0188 | May 23, 2025 | REHABILITATION OF MULTI-PURPOSE BUILDING, SAN JOSE PATROCINIO ELEMENTARY SCHOOL, SAN NARCISO, ZAMBALES | On-Going | ₱14.7M |
| 25CL0192 | May 23, 2025 | CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG STO. TOMAS RIVER (MACULCOL DIKE) SOUTH APPROACH, PHASE 1, SAN NARCISO, ZAMBALES | On-Going | ₱96.4M |
| 25CL0193 | May 23, 2025 | CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG STO. TOMAS RIVER (MACULCOL DIKE) SOUTH APPROACH, PHASE 2, SAN NARCISO, ZAMBALES | On-Going | ₱96.5M |
| 25CL0194 | May 23, 2025 | CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG STO. TOMAS RIVER (MACULCOL DIKE) SOUTH APPROACH, PHASE 3, SAN NARCISO, ZAMBALES | On-Going | ₱96.4M |
| 25CL0195 | May 23, 2025 | CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG STO. TOMAS RIVER (MACULCOL DIKE) SOUTH APPROACH, PHASE 4, SAN NARCISO, ZAMBALES | On-Going | ₱96.4M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.