Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 23CN0082

DPWH infrastructure contract
Hashed input (canonical JSON of the source row)
["dpwh","23CN0082","CONSTRUCTION OF MULTI-PURPOSE BUILDING (COMMAND CENTER), BALER, AURORA","Buildings and Facilities","Completed",29068077.41,0,100,"Aurora DEO","Region III","GASAT BUILDERS AND SUPPLIES INC. (51666)","2023-04-27","2024-01-03",2023,"Regular Infra - GAA 2023 CSSP",15.75949,121.56284,"307701000","307700000"]
SHA-256
4f2e3c55604d16632c61b68a9601ee451881f4c972b12cee605bf39c4baa1444

Hash the line above with SHA-256 to reproduce the fingerprint. It proves the record is unchanged since import. It is not a blockchain entry, and it cannot prove the source data is accurate.