Project 23DB0155
DPWH infrastructure contract
Contract ID:
23DB0155
Fingerprint:
0fe975275951bf…852eb868af Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Oct 13, 2023 (3 yrs 1 mo ago) · Target/actual end Jun 26, 2024
Description:
CONSTRUCTION OF 2STY6CL BULIHAN ELEMENTARY SCHOOL, NASUGBU, BATANGAS
Category:
Buildings and Facilities
Implementing office:
DPWH Batangas 1st DEO · Region IV-A
Contractor:
FRAMECON BUILDERS · DPWH contractor code 22482
Contract amount:
₱30,000,000.00 (₱30.0M)
Funding source:
Outside Infra - GAA 2023 DepEd BEFF
Budget year:
2023
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| c57f7e95122d… | Oct 6, 2023 | DPWH - BATANGAS 1ST DISTRICT ENGINEERING OFFICE | ₱29,099,985.00 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25DB0188 | Jul 25, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY 5, NASUGBU, BATANGAS | Completed | ₱4.9M |
| 25DB0200 | Jul 25, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - REHABILITATION OF MULTI-PURPOSE BUILDING AT BARANGAY BALAY TIGUE, NASUGBU, BATANGAS | Completed | ₱9.6M |
| 25DB0164 | Jul 18, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - COMPLETION OF MULTI-PURPOSE BUILDING IN TUMALIM ELEMENTARY SCHOOL, BRGY. TUMALIM, NASUGBU, BATANGAS | Completed | ₱2.9M |
| 25DB0209 | Jul 9, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - PUBLIC WATER SUPPLY SYSTEM - CONSTRUCTION OF PUBLIC WATER SYSTEM AT BARANGAY BUTUCAN, NASUGBU, BATANGAS | Completed | ₱4.8M |
| 25DB0150 | Jul 7, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF CANAL AT BARANGAY WAWA, NASUGBU, BATANGAS | Completed | ₱4.8M |
| 25DB0174 | Jul 7, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - COMPLETION OF MULTI-PURPOSE BUILDING AT BARANGAY PANTALAN, NASUGBU, BATANGAS | Completed | ₱2.9M |
| 25D00099 | Jun 23, 2025 | CONSTRUCTION OF MISSING LINKS/ NEW ROADS GENERAL AGUINALDO-MAGALLANES-NASUGBU ROAD (EAST-WEST ROAD), NASUGBU SECTION, BATANGAS | On-Going | ₱34.0M |
| 25DB0175 | Jun 17, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) AT BARANGAY 5, NASUGBU, BATANGAS | Completed | ₱4.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.