Physical progress:
100%
Timeline:
Start May 2, 2023 (3 yrs 6 mo ago) · Target/actual end Dec 1, 2023
Description:
CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/FACILITIES, REHABILITATION OF SLOPE PROTECTION STRU
Category:
Roads
Implementing office:
DPWH Quezon 2nd DEO · Region IV-A
Contractor:
SILVERWOLVES CONSTRUCTION CORPORATION · DPWH contractor code 48466
Contract amount:
₱96,498,225.44 (₱96.5M)
Funding source:
Regular Infra - GAA 2023 CSSP
Budget year:
2023
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| d7faade66f07… | Apr 19, 2023 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - QUEZON 2ND ED | ₱91,438,672.33 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25DJ0108 | Jun 5, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY BULAKIN 2, DOLORES, QUEZON | On-Going | ₱2.4M |
| 25DJ0110 | Jun 5, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION/REHABILITATION OF MULTI-PURPOSE BUILDING, BARANGAY KINABUHAYAN, DOLORES, QUEZON | On-Going | ₱4.8M |
| 25DJ0125 | Jun 5, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (MUNICIPAL TRADING CENTER) IN DOLORES, QUEZON | On-Going | ₱4.8M |
| 25DJ0096 | Mar 31, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - PUBLIC WATER SUPPLY SYSTEM, CONSTRUCTION OF WATER SUPPLY SYSTEM, BARANGAY ANTONINO, DOLORES, QUEZON | Completed | ₱9.6M |
| 25DJ0009 | Mar 5, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SANTA LUCIA, DOLORES, QUEZON | Completed | ₱7.3M |
| 25DJ0032 | Mar 5, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDING/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING, MANGGAHAN SCHOOL, BARANGAY MANGGAHAN, DOLORES, QUEZON | Completed | ₱7.3M |
| 25DJ0062 | Mar 5, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY MANGGAHAN, DOLORES, QUEZON | Completed | ₱2.9M |
| 25DJ0078 | Mar 5, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - PUBLIC WATER SUPPLY SYSTEM, CONSTRUCTION OF WATER SUPPLY SYSTEM, BARANGAY PINAGDANLAYAN, DOLORES, QUEZON | On-Going | ₱19.6M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.