Project 23DN0124
DPWH infrastructure contract
Contract ID:
23DN0124
Fingerprint:
303a7c398c6201…5671c1f73e Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 26, 2023 (3 yrs 3 mo ago) · Target/actual end Sep 24, 2024
Description:
CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAINWATER COLLECTORS - WATER SUPPLY SYSTEM - CONSTRUCTION OF SOLAR WATER SYSTEM, TAYTAY, RIZAL (FIRST DISTRICT)
Category:
Water Provision and Storage
Implementing office:
DPWH Rizal 1st DEO · Region IV-A
Contractor:
DJL ROBLES BUILDERS · DPWH contractor code 39672
Contract amount:
₱9,799,572.75 (₱9.8M)
Funding source:
Regular Infra - GAA 2023 CSSP
Budget year:
2023
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 022448ed80b3… | Jul 13, 2023 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - RIZAL 1ST ED | ₱9,504,498.64 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25O00107 | Jun 5, 2025 | REHABILITATION AND IMPROVEMENT OF RETARDING POND AT TAPAYAN PUMPING STATION AND TRIBUTARIES, PASIG CITY | On-Going | ₱189.1M |
| 25OB0268 | May 20, 2025 | REHABILITATION OF DRAINAGE SYSTEM AT BARANGAY PINAGBUHATAN, PASIG CITY (PHASE 5) | On-Going | ₱14.0M |
| 25OB0269 | May 20, 2025 | REHABILITATION OF DRAINAGE SYSTEM AT BARANGAY PINAGBUHATAN, PASIG CITY (PHASE 6) | On-Going | ₱14.0M |
| 25OB0270 | May 20, 2025 | REHABILITATION OF DRAINAGE SYSTEM AT BARANGAY PINAGBUHATAN, PASIG CITY (PHASE 7) | On-Going | ₱14.0M |
| 25DN0069 | Apr 8, 2025 | CONSTRUCTION OF ROAD AT ROAD 11, 12, 13, 14, 15, 16 AND 17, PUROK 3, LUPANG ARENDA, BARANGAY STA. ANA, TAYTAY, RIZAL (FIRST DISTRICT) | On-Going | ₱19.6M |
| 25DN0063 | Mar 27, 2025 | CONSTRUCTION OF MULTI-PURPOSE FACILITY, RIZAL POLICE PROVINCIAL OFFICE, BARANGAY DOLORES, TAYTAY, RIZAL (FIRST DISTRICT) | On-Going | ₱9.7M |
| 25DN0080 | Mar 27, 2025 | CONSTRUCTION OF ROAD AT BLK. 16 AND 17, PUROK 2 LUPANG ARENDA, BARANGAY STA. ANA, TAYTAY, RIZAL (FIRST DISTRICT) | On-Going | ₱15.2M |
| 25DN0048 | Mar 26, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT TAYTAY RIVER, BARANGAY STA. ANA, TAYTAY, RIZAL (FIRST DISTRICT) | On-Going | ₱49.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.