Project 23DN0133
DPWH infrastructure contract
Contract ID:
23DN0133
Fingerprint:
912ec19560d183…75f4475f47 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Aug 22, 2023 (3 yrs 2 mo ago) · Target/actual end Mar 22, 2024
Description:
CONSTRUCTION OF FOUR (4) STOREY, EIGHT (8) CL, DOÑA SUSANA MADRIGAL E/S BINANGONAN, RIZAL (FIRST DISTRICT)
Category:
Buildings and Facilities
Implementing office:
DPWH Rizal 1st DEO · Region IV-A
Contractor:
MICLOVER GENERAL CONSTRUCTION AND IRON WORKS · DPWH contractor code 31527
As listed: MICLOVER GENERAL CONSTRUCTION & IRON WORKS
Contract amount:
₱30,000,000.00 (₱30.0M)
Funding source:
Outside Infra - GAA 2023 DepEd BEFF
Budget year:
2023
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| a184757352da… | Aug 15, 2023 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - RIZAL 1ST ED | ₱29,837,962.65 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25DN0097 | Jun 26, 2025 | ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - SECONDARY ROADS - MANILA EAST RD - K0033+276 - K0033+551, RIZAL (FIRST DISTRICT) | On-Going | ₱7.1M |
| 25DN0098 | May 29, 2025 | CONSTRUCTION OF ROAD AT BARANGAY ITHAN TO BARANGAY KALINAWAN, BINANGONAN, RIZAL (FIRST DISTRICT) | On-Going | ₱19.0M |
| 25DN0101 | May 29, 2025 | CONSTRUCTION OF FLOOD STRUCTURE, CREEK, W. CERRERO GOING TO F. CEQUEÑA, BARANGAY MACAMOT, BINANGONAN, RIZAL (FIRST DISTRICT) | Completed | ₱9.5M |
| 25DN0106 | May 29, 2025 | CONSTRUCTION OF BOX CULVERT CONNECTING BARANGAY JANOSA AND BARANGAY KAYTOME BINANGONAN, RIZAL (FIRST DISTRICT) | On-Going | ₱4.9M |
| 25DN0112 | May 29, 2025 | FY 2025 CONVERGENCE AND SPECIAL SUPPORT PROGRAM - RAINWATER COLLECTOR SYSTEM BINANGONAN, RIZAL (FIRST DISTRICT) | On-Going | ₱2.6M |
| 25DN0067 | May 27, 2025 | CONSTRUCTION OF ROAD AT CABLE WAY GOING TO KASINAY, BARANGAY MACAMOT AND BARANGAY DARANGAN, BINANGONAN, RIZAL (FIRST DISTRICT) | Completed | ₱67.5M |
| 25DN0044 | May 26, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE, SAN JUAN CREEK, BINANGONAN, RIZAL (FIRST DISTRICT) | Completed | ₱19.6M |
| 25DN0056 | May 26, 2025 | CONSTRUCTION OF BREAKWATER, BARANGAY KALINAWAN GOING TO BARANGAY PIPINDAN, BINANGONAN, RIZAL (FIRST DISTRICT) | On-Going | ₱9.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.