Project 23E00128
DPWH infrastructure contract
Contract ID:
23E00128
Fingerprint:
d727f6fcd13bdb…34f3d9b44b Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 13, 2023 (3 yrs 7 mo ago) · Target/actual end Dec 15, 2023
Description:
SUSTAINABLE INFRA. PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES-CONST. OF FLOOD CONTROL STRUCTURE ALONG LIBTANGIN RIVER, BRGY. MANGILIOL SECT., GASAN, MARINDUQUE
Category:
GAA 2023 CSSP
Implementing office:
DPWH MIMAROPA Region · MIMAROPA Region
Contractor:
Location:
Contract amount:
₱241,248,643.68 (₱241.2M)
Funding source:
Regular Infra - GAA 2023 CSSP
Budget year:
2023
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 3045f1066e64… | Mar 28, 2023 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - REGION IV-B | ₱232,522,402.90 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25EA0102 | Mar 10, 2026 | LAST MILE SCHOOLS PROGRAM - BACONGBACONG ES, GASAN, MARINDUQUE | On-Going | ₱10.8M |
| 25EA0100 | Feb 2, 2026 | REPAIR/REHABILITATION OF CLASSROOMS, BOGNUYAN ES, GASAN, MARINDUQUE | On-Going | ₱8.0M |
| 25EA0018 | Mar 21, 2025 | NETWORK DEVELOPMENT PROGRAM, ROAD WIDENING - SECONDARY ROADS, MARINDUQUE CIRCUMFERENTIAL RD - K0095+526 - K0097+077, K0097+137 - K0097+812 | Completed | ₱103.0M |
| 25EA0033 | Mar 21, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (PHASE 2), BARANGAY LIBTANGIN, GASAN, MARINDUQUE | Completed | ₱2.9M |
| 25EA0002 | Feb 21, 2025 | FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM, CONSTRUCTION OF MASIGA FLOOD CONTROL STRUCTURE, BARANGAY MASIGA, GASAN, MARINDUQUE | Completed | ₱38.8M |
| 24EA0096 | Jan 28, 2025 | SIPAG - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF TIGUION RIVER CONTROL, GASAN, MARINDUQUE | Completed | ₱48.2M |
| 24EA0063 | Mar 18, 2024 | CONCRETING OF BRGY. BOGNUYAN FMR PHASE II, BRGY. BOGNUYAN, GASAN,MARINDUQUE | Completed | ₱14.9M |
| 24EA0072 | Mar 15, 2024 | CONSTRUCTION OF BAHI-TAPUYAN ROAD, GASAN, MARINDUQUE | Completed | ₱96.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.