Project 23ED0026
DPWH infrastructure contract
Contract ID:
23ED0026
Fingerprint:
019a2fc4f934e8…d774a60bb4 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 23, 2023 (3 yrs 7 mo ago) · Target/actual end Sep 25, 2023
Description:
CONSTRUCTION OF LEVEL II POTABLE WATER SYSTEM AT SUBAAN - LEUTEBORO, SOCORRO, ORIENTAL MINDORO
Category:
GAA 2023 CSSP
Implementing office:
DPWH Mindoro Oriental DEO · MIMAROPA Region
Contractor:
JCL86 BUILDERS INC. · DPWH contractor code 52891
Contract amount:
₱9,799,672.56 (₱9.8M)
Funding source:
Regular Infra - GAA 2023 CSSP
Budget year:
2023
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| bb59a2f47735… | Mar 7, 2023 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - MINDORO ORIENTAL D | ₱9,652,351.17 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25ED0105 | May 26, 2025 | PREVENTIVE MAINTENANCE ALONG CALAPAN SOUTH ROAD - K0046+000 - K0047+462, ORIENTAL MINDORO | Completed | ₱115.8M |
| 25ED0106 | May 26, 2025 | PREVENTIVE MAINTENANCE ALONG CALAPAN SOUTH ROAD - K0049+000 - K0050+765, ORIENTAL MINDORO | Completed | ₱82.0M |
| 25ED0108 | May 26, 2025 | INSTALLATION OF STREET LIGHTS ALONG CALAPAN SOUTH ROAD K0047+200 - K0060+800, SOCORRO, ORIENTAL MINDORO | Completed | ₱95.1M |
| 25ED0123 | May 26, 2025 | PREVENTIVE MAINTENANCE ALONG CALAPAN SOUTH ROAD - K0062+000 - K0063+015, ORIENTAL MINDORO | Completed | ₱106.1M |
| 25ED0125 | May 26, 2025 | PREVENTIVE MAINTENANCE ALONG CALAPAN SOUTH ROAD K0050+765 - K0052+246, ORIENTAL MINDORO | Completed | ₱86.8M |
| 25ED0126 | May 26, 2025 | PREVENTIVE MAINTENANCE ALONG CALAPAN SOUTH ROAD K0052+246 - K0053+511, ORIENTAL MINDORO | On-Going | ₱57.9M |
| 25ED0127 | May 26, 2025 | PREVENTIVE MAINTENANCE ALONG CALAPAN SOUTH ROAD K0061+129 - K0062+000, ORIENTAL MINDORO | Completed | ₱72.4M |
| 25ED0134 | May 26, 2025 | REHABILITATION OF BRGY. LEUTEBORO I - BRGY. MATUNGAO ROAD, SOCORRO, ORIENTAL MINDORO | Completed | ₱144.1M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.