Project 23EH0169
DPWH infrastructure contract
Contract ID:
23EH0169
Fingerprint:
857fd363df330b…853e61a926 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Nov 22, 2023 (2 yrs 11 mo ago) · Target/actual end Dec 29, 2023
Description:
CONSTRUCTION/REHABILITATION OF ACCESS ROAD TO NATIONAL ROAD FROM DON MODESTO FORMILLEZA SR. MEMORIAL HOSPITAL SITIO ALONG THE ROAD TO BRGY. PUNTA, LOOC, ROMBLON, LOOC, ROMBLON
Category:
Unprogrammed Appropriations 2023
Implementing office:
DPWH Romblon DEO · MIMAROPA Region
Contractor:
TABLAS CONSTRUCTION CORPORATION · DPWH contractor code 45015
Location:
Contract amount:
₱4,820,990.35 (₱4.8M)
Funding source:
Outside Infra - Unprogrammed Appropriations 2023
Budget year:
2023
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 13e5fee1d863… | Oct 31, 2023 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ROMBLON DEO | ₱4,820,990.35 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26EH0032 | Aug 11, 2026 | REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - LOOC (COGON TULAY) - ODIONGAN RD - K0103+198-K0103+330.70, K0103+338.56 - K0103+362.50, TABLAS ISLAND, ROMBLON | On-Going | ₱4.4M |
| 25EH0084 | Jul 28, 2025 | ROAD WIDENING ALONG TABLAS CIRCUMFERENTIAL ROAD, K0098+820.00-K0099+202.90, K0099+231.13 - K0100+350.23 (AS PER ACTUAL), K0098+820.00-K0099+199.90, K0099+231.13 - K0100+341.23 (AS PER RBIA), TABLAS ISLAND, ROMBLON | On-Going | ₱96.2M |
| 25EH0129 | Jul 10, 2025 | CONSTRUCTION OF LIMON NORTE WATER IMPOUNDING PROJECT, LOOC, ROMBLON | On-Going | ₱48.0M |
| 25EH0155 | May 27, 2025 | CONSTRUCTION OF ROAD, PHASE 2, BARANGAY BAGSIK - SITIO LOBTON TO BARANGAY MADALAG (ALCANTARA) LEADING TO BARANGAY TUGUIS, LOOC, ROMBLON | On-Going | ₱93.6M |
| 25EH0158 | May 27, 2025 | CONSTRUCTION OF BRGY. PILI TO BRGY. LIMON SUR ROAD (PHASE 2), LOOC, ROMBLON | On-Going | ₱119.9M |
| 25EH0022 | May 26, 2025 | CONSTRUCTION OF CAUSEWAY ALONG PUNTA, LOOC, ROMBLON, TABLAS ISLAND, ROMBLON | On-Going | ₱71.3M |
| 25EH0109 | May 26, 2025 | COMPLETION OF MULTI-PURPOSE BUILDING (GOVERNMENT CENTER) AT BARANGAY PUNTA, LOOC, ROMBLON | On-Going | ₱9.7M |
| 25EH0114 | May 26, 2025 | COMPLETION OF MULTI-PURPOSE BUILDING AT BARANGAY TUGUIS, LOOC, ROMBLON | Completed | ₱4.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.