Project 23EH0188
DPWH infrastructure contract
Contract ID:
23EH0188
Fingerprint:
a6899a6d5b796e…ff498a1f7b Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 18, 2024 (2 yrs 6 mo ago) · Target/actual end Sep 23, 2024
Description:
CONSTRUCTION OF ROAD, BRGY. AGPUDLOS LEADING TO RSU ROAD, SAN ANDRES, ROMBLON
Category:
Unprogrammed Appropriations 2023
Implementing office:
DPWH Romblon DEO · MIMAROPA Region
Contractor:
SUNWEST, INC. · DPWH contractor code 15906
As listed: SUNWEST, INC. (FORMERLY: SUNWEST CONSTRUCTION & DEVELOPMENT CORPORATION)
Contract amount:
₱48,250,000.00 (₱48.3M)
Funding source:
Outside Infra - Unprogrammed Appropriations 2023
Budget year:
2023
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 7e4c2aff0f8e… | Mar 26, 2024 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ROMBLON DEO | ₱47,544,294.63 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25EH0167 | Jul 29, 2025 | CONSTRUCTION OF 7 RAINWATER COLLECTION SYSTEM (RWCS), TABLAS ISLAND, ROMBLON | Completed | ₱2.6M |
| 25EH0151 | May 27, 2025 | CONSTRUCTION OF ROAD, AGPUDLOS LEADING TO RSU ROAD (PHASE 3), SAN ANDRES, ROMBLON | On-Going | ₱46.7M |
| 25EH0121 | May 21, 2025 | CONSTRUCTION OF VICTORIA RIVER FLOOD CONTROL STRUCTURE, SAN ANDRES, ROMBLON | On-Going | ₱119.4M |
| 25EH0030 | Apr 11, 2025 | CONSTRUCTION OF MABINI FLOOD CONTROL STRUCTURE, BARANGAY MABINI, SAN ANDRES, ROMBLON | On-Going | ₱48.3M |
| 25EH0090 | Apr 10, 2025 | CONSTRUCTION OF MARI-SUR FLOOD CONTROL STRUCTURE (RIGHT SIDE), SAN ANDRES, ROMBLON | On-Going | ₱48.3M |
| 25EH0012 | Mar 24, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY VICTORIA, SAN ANDRES, ROMBLON | Completed | ₱4.9M |
| 25EH0062 | Mar 3, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY MABINI, SAN ANDRES, ROMBLON | Completed | ₱2.9M |
| 24EH0131 | Jun 19, 2024 | REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE ALONG PARPAGOHA (MARIGONDON)-BINOOG RD, K0020+900.00 - K0020+985.60, TABLAS ISLAND, ROMBLON | On-Going | ₱82.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.