Project 23F00025
DPWH infrastructure contract
Contract ID:
23F00025
Fingerprint:
0047f6b55d5b89…bf638955eb Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 30, 2023 (3 yrs 7 mo ago) · Target/actual end Feb 27, 2024
Description:
OO2:PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF REVETMENT ALONG QUINALE RIVER, DOWNSTREAM OF COMUN BRI
Category:
Flood Control and Drainage
Implementing office:
DPWH Region V · Region V
Contractor:
MAKAPA CORPORATION · DPWH contractor code 30029
Contract amount:
₱101,324,139.60 (₱101.3M)
Funding source:
Regular Infra - GAA 2023 OO-2
Budget year:
2023
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| dbbcfb8ed5cb… | Mar 14, 2023 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - REGION V | ₱97,777,806.25 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25FA0026 | Jun 25, 2025 | PREVENTIVE MAINTENANCE-SECONDARY ROADS:DAANG MAHARLIKA JCT-LEGAZPI-STO. DOMINGO-TABACO-CAM. SUR BDRY. ROAD K0561+022-K0561+552 | On-Going | ₱42.6M |
| 25FA0017 | Mar 7, 2025 | CONSTRUCTION OF RIVER CONTROL, MALOLOS, MALINAO, ALBAY | Completed | ₱38.6M |
| 25FA0007 | Feb 21, 2025 | CONSTRUCTION OF SLOPE PROTECTION WORKS AT SAGPAN KAN BANWA CIS, MALINAO, ALBAY | Completed | ₱13.9M |
| 24FA0063 | Oct 7, 2024 | CONSTRUCTION OF 2STY6CL, OGOB ELEMENTARY SCHOOL, MALINAO, ALBAY | On-Going | ₱35.7M |
| 24F00425 | Sep 20, 2024 | CAPITAL OUTLAY - DOH HEALTH FACILITIES ENHANCEMENT PROGRAM (HFEP) - CONSTRUCTION OF NEW SUPER HEALTH CENTERS/RHU - MALINAO SUPER HEALTH CENTER, ALBAY, MALINAO, ALBAY (1ST LEGISLATIVE DISTRICT) | On-Going | ₱11.9M |
| 24FA0056 | Aug 16, 2024 | CLUSTER 13- ASPHALT OVERLAY MAHARLIKA JCT LEGAZPI-STO. DOMINGO-TABACO-CAM SUR BDRY ROAD K0560+395-K0561+022, MALINAO, ALBAY AND ASPHALT OVERLAY- LIGAO-TABACO ROAD K0520+379-K0520+723, TABACO CITY, ALBAY | Completed | ₱79.4M |
| 23FA0091 | Jun 26, 2024 | CLUSTER 29- CONST. OF ELEM. SCHOOL BLDGS. (CLASSROOMS) IN THE FIRST DISTRICT OF ALBAY | Completed | ₱41.4M |
| 24FA0038 | Jun 26, 2024 | RAINWATER COLLECTORS IN PUBLIC FACILITIES IN THE FIRST DISTRICT OF ALBAY | On-Going | ₱2.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.