Project 23FA0072

DPWH infrastructure contract
Contract ID:
23FA0072
Fingerprint:
7fc8f092da863e…22d8ff863f Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Dec 6, 2023 (2 yrs 11 mo ago) · Target/actual end May 9, 2024
Description:
CONSTRUCTION OF SOLAR WATER SYSTEM, TIWI, ALBAY
Category:
Water Provision and Storage
Implementing office:
DPWH Albay 1st DEO · Region V
Contractor:
JORMAND CONSTRUCTION & SUPPLY · DPWH contractor code 40760
Contract amount:
₱9,800,000.00 (₱9.8M)
Funding source:
Regular Infra - GAA 2023 CSSP
Budget year:
2023