Project 23FG0003
DPWH infrastructure contract
Contract ID:
23FG0003
Fingerprint:
510d05039f970e…65b089613c Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 19, 2023 (3 yrs 8 mo ago) · Target/actual end Jun 24, 2023
Description:
CONSTRUCTION / UPGRADING / REHABILITATION OF DRAINAGE ALONG NATIONAL ROAD, LAGONOY-PRESENTACION ROAD K0525+029 - K0525+079, K0527+175 - K0527+200, PRESENTACION, CAMARINES SUR
Category:
Roads
Implementing office:
DPWH Camarines Sur 4th DEO · Region V
Contractor:
PARTIDO CONSTRUCTION & SUPPLY · DPWH contractor code 20631
Contract amount:
₱7,840,000.00 (₱7.8M)
Funding source:
Regular Infra - GAA 2023 OO-1
Budget year:
2023
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 83a4d33c64fc… | Feb 6, 2023 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CAMARINES SUR 4TH | ₱7,512,199.33 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26FG0035 | Jul 17, 2026 | REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS ALONG LAGONOY - PRESENTACION RD K0519+797 - K0519+955; K0521+1022 - K0522+860; K0524+385 - K0524+660 PRESENTACION, CAMARINES SUR | On-Going | ₱34.5M |
| 25FG0054 | Jun 30, 2025 | CONSTRUCTION OF WATER SUPPLY SYSTEM, BARANGAY ADIANGAO, SAN JOSE, CAMARINES SUR TO BARANGAY AYUGAO, BARANGAY LAGHA AND BARANGAY CAGNIPA, PRESENTACION, CAMARINES SUR SAN JOSE AND PRESENTACION, CAMARINES SUR | On-Going | ₱19.0M |
| 25FG0084 | Jun 9, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, PRESENTACION, CAMARINES SUR | Completed | ₱9.5M |
| 25FG0038 | Mar 27, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY BUENAVISTA, PRESENTACION, CAMARINES SUR | Completed | ₱1.9M |
| 24FG0118 | Sep 9, 2024 | CONCRETING OF BRGY. BANTUGAN FMR, BRGY. BANTUGAN, PRESENTACION, CAMARINES SUR | On-Going | ₱9.5M |
| 24FG0113 | Jul 3, 2024 | CONCRETING OF BRGY. BICALEN - BRGY. BANTUGAN FMR PHASE 1 (BANTUGAN SECTION), BRGY. BANTUGAN, PRESENTACION, CAMARINES SUR | Completed | ₱14.5M |
| 24FG0102 | May 30, 2024 | CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM, CAMARINES SUR 4TH LEGISLATIVE DISTRICT | Completed | ₱2.8M |
| 24FG0085 | May 3, 2024 | CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN BALIGUIAN HIGH SCHOOL (PRESENTACION NSH ANNEX) BARANGAY BALIGUIAN, PRESENTACION, CAMARINES SUR | Completed | ₱7.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.