Project 23GA0223

DPWH infrastructure contract
Contract ID:
23GA0223
Fingerprint:
4b0e5610d08051…3d9568e7de Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 28, 2024 (2 yrs 5 mo ago) · Target/actual end Dec 14, 2024
Description:
CONSTRUCTION OF ROAD SAFETY: STREET LIGHTING - KALIBO CIRCUMFERENTIAL ROAD (TIGAYON SECTION) AKLAN
Category:
Unprogrammed Appropriations 2023
Implementing office:
DPWH Aklan DEO · Region VI
Contract amount:
₱149,568,862.13 (₱149.6M)
Funding source:
Outside Infra - Unprogrammed Appropriations 2023
Budget year:
2023

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25GA0133Jul 22, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG AKLAN RIVER, BARANGAY CAMANCI NORTE, NUMANCIA, AKLANOn-Going₱88.3M
25GA0095Jun 3, 2025COMPLETION OF MULTI-PURPOSE BUILDING, BARANGAY LAGUINBANUA WEST, NUMANCIA, AKLANOn-Going₱2.0M
25GA0097Jun 3, 2025COMPLETION OF MULTI-PURPOSE BUILDING, BARANGAY PUSIW, NUMANCIA, AKLANOn-Going₱2.0M
25GA0099Jun 3, 2025COMPLETION OF MULTI-PURPOSE BUILDING, BARANGAY BULWANG, NUMANCIA, AKLANCompleted₱2.4M
25GA0116Jun 3, 2025CONSTRUCTION/COMPLETION OF MULTI-PURPOSE BUILDING, BARANGAY DONGON EAST, NUMANCIA, AKLANOn-Going₱3.0M
25GA0139Jun 3, 2025COMPLETION OF MULTI-PURPOSE BUILDING, BARANGAY JOYAO JOYAO, NUMANCIA, AKLANOn-Going₱2.0M
25GA0098May 23, 2025REHABILITATION OF MULTI-PURPOSE BUILDING, BARANGAY NAVITAS, NUMANCIA, AKLANOn-Going₱3.7M
25GA0117May 23, 2025CONSTRUCTION/COMPLETION OF MULTI-PURPOSE BUILDING, BARANGAY MARIANOS, NUMANCIA, AKLANOn-Going₱2.4M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.