Project 23GB0044
DPWH infrastructure contract
Contract ID:
23GB0044
Fingerprint:
a29349d91deca0…9f02823e91 Verified
Status:
On-Going
Physical progress:
95.0%
Timeline:
Start Mar 30, 2023 (3 yrs 7 mo ago)
Description:
ALANGAN - CUBAY - SIBALOM RD - K108 + 000 - K0108 + 833
Category:
Roads
Implementing office:
DPWH Antique DEO · Region VI
Contractor:
ALLENCON DEVELOPMENT CORPORATION · DPWH contractor code 12302
Contract amount:
₱9,372,701.69 (₱9.4M)
Funding source:
Regular Infra - GAA 2023 OO-1
Budget year:
2023
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| e4de23db2fba… | Mar 16, 2023 | DPWH - ANTIQUE DISTRICT ENGINEERING OFFICE | ₱9,320,000.00 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26GB0095 | Jun 18, 2026 | PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - ALANGAN-CUBAY-SIBALOM RD - K0107 + 000 - K0107+1010, SIBALOM, ANTIQUE | On-Going | ₱18.0M |
| 26GB0096 | Jun 1, 2026 | RECONSTRUCTION TO CONCRETE PAVEMENT - ALANGAN-CUBAY-SIBALOM RD - K0107+(-552) - K0107+000, SIBALOM, ANTIQUE | On-Going | ₱9.1M |
| 25GB0136 | Aug 8, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING AT THE UNIVERSITY OF ANTIQUE AT SIBALOM, ANTIQUE | On-Going | ₱19.8M |
| 25GB0072 | May 30, 2025 | PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - BANTAYAN - SN PEDRO - CUBAY RD - CHAINAGE 0 - CHAINAGE 714, ANTIQUE | On-Going | ₱28.8M |
| 25GB0075 | May 30, 2025 | PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - SIBALOM - PISANAN RD - K0107+(-078) - K0109+000, ANTIQUE | On-Going | ₱40.5M |
| 25GB0121 | May 30, 2025 | SIBALOM-UNIVERSITY OF ANTIQUE DIVERSION ROAD, ANTIQUE | On-Going | ₱44.0M |
| 25GB0031 | Mar 4, 2025 | CONSTRUCTION OF CONCRETE ROAD INCLUDING DRAINAGE AND SLOPE PROTECTION- BRGY. TULA-TULA- BRGY. CALU-OY-BRGY. BULALACAO CIRCUMFERENTIAL ROAD CONNECTING TO PUBLIC MARKET OF SIBALOM IN SUPPORT OF AGRIBUSINESS INDUSTRY (COFFEE,ROOTCROPS, PEANUTS AND GINGER), S | Completed | ₱4.9M |
| 25GB0055 | Mar 4, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, SITIO APONG, BARANGAY CABLADAN, SIBALOM,ANTIQUE | Completed | ₱4.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.