Project 23GD0058
DPWH infrastructure contract
Contract ID:
23GD0058
Fingerprint:
dddf064de34179…d14bc8623d Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 8, 2023 (3 yrs 6 mo ago) · Target/actual end Jun 6, 2023
Description:
CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAINWATER COLLECTOR SYSTEM 1. AGUSTIN A. ALMALBIS MEM. SCHL. 2. FELIXBERTO DICON DORADO SR. INT. SCHL. 3. QUIOS PRI SCHL. 4. BRGY. BAHIT MPB 5. BRGY. SAN FERNANDO MPB 6. BRGY. SAN PEDRO MPB
Category:
Water Provision and Storage
Implementing office:
DPWH Capiz 1st DEO · Region VI
Contractor:
MAKANA BUILDERS & SUPPLY · DPWH contractor code 39826
Contract amount:
₱2,269,680.00 (₱2.3M)
Funding source:
Regular Infra - GAA 2023 CSSP
Budget year:
2023
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25GD0062 | Jul 14, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY TACAS, PONTEVEDRA, CAPIZ | On-Going | ₱6.9M |
| 25GD0050 | Jul 8, 2025 | PONTEVEDRA BY-PASS ROAD, CAPIZ | On-Going | ₱8.2M |
| 25GD0052 | Jul 8, 2025 | ROAD WIDENING - ILOILO EAST COAST-CAPIZ ROAD - KO146+781 - KO147+001 | Completed | ₱8.3M |
| 25G00071 | May 20, 2025 | CONSTRUCTION OF MULTI- PURPOSE BUILDING (EVACUATION FACILITIES), BARANGAY RIZAL, PONTEVEDRA, CAPIZ | On-Going | ₱48.2M |
| 25GD0028 | Mar 31, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION ILAWOD, PONTEVEDRA, CAPIZ | On-Going | ₱4.9M |
| 25GD0006 | Mar 24, 2025 | RECONSTRUCTION TO CONCRETE PAVEMENT - ILOILO EAST COAST - CAPIZ RD - KO135+778 - KO136+302 | On-Going | ₱8.5M |
| 25GD0014 | Mar 24, 2025 | CONSTRUCTION OF CONCRETE ROAD - CONSTRUCTION OF ROAD, BARANGAY JOLONGAJOG, PONTEVEDRA, CAPIZ | On-Going | ₱4.9M |
| 24GD0067 | Nov 14, 2024 | CONCRETING OF SITIO CARINGALA, BRGY. JOLONGAJOG FMR, BRGY. JOLONGAJOG, PONTEVEDRA, CAPIZ | On-Going | ₱11.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.