Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 23GH0159

DPWH infrastructure contract
Contract ID:
23GH0159
Fingerprint:
45e0aa20e268ac…476b774a43 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Sep 6, 2023 (3 yrs 2 mo ago) · Target/actual end Feb 12, 2024
Description:
CONSTRUCTION OF 1 STY 2 CL, BULAK INTEGRATED SCHOOL, BATAD, ILOILO
Category:
Buildings and Facilities
Implementing office:
DPWH Iloilo 3rd DEO · Region VI
Contractor:
EARLY RISER CONSTRUCTION · DPWH contractor code 33960
Contract amount:
₱6,310,000.00 (₱6.3M)
Funding source:
Outside Infra - GAA 2023 DepEd BEFF
Budget year:
2023

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
dd99f0a4e09f…Aug 18, 2023DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ILOILO 3RD DEO₱6,238,962.00

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25GH0125Mar 25, 2025CONSTRUCTION (COMPLETION) OF MULTI- PURPOSE BUILDING, BARANGAY SALONG, BATAD, ILOILOCompleted₱2.9M
25GH0095Mar 24, 2025CONSTRUCTION (COMPLETION) OF MULTI- PURPOSE BUILDING, BARANGAY STA. ANA, BATAD, ILOILOCompleted₱3.0M
25GH0056Feb 19, 2025UPGRADING OF DRAINAGE STRUCTURE ALONG ROAD- ILOILO EAST COAST- CAPIZ RD- K0184+860Completed₱4.9M
25GH0069Feb 19, 2025CONSTTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY PASAYAN, BATAD, ILOILOCompleted₱2.0M
25GH0059Feb 17, 2025CONSTRUCTION (COMPLETION) OF MULTI- PURPOSE BUILDING, BARANGAY ALAPASCO, BATAD, ILOILOCompleted₱3.0M
25GH0063Feb 17, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY CALANGAG, BATAD, ILOILOOn-Going₱3.0M
24GH0187Oct 17, 2024CONSTRUCTION/REHABILITATION/IMPROVEMENT OF FACILITIES FOR PERSONS WITH DISABILITIES (PWD) AND ELDERLIES/SENIOR CITIZENS, INCLUDING GENDER-RESPONSIVE FACILITIES, BINON-AN ELEMENTARY SCHOOL, BARANGAY BINON-AN, BATAD, ILOILOOn-Going₱1.0M
24GH0177Jun 20, 2024COMPLETION OF MULTIPURPOSE BUILDING, CABAGOHAN, BATAD, ILOILOCompleted₱2.0M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.