Project 23GI0055
DPWH infrastructure contract
Contract ID:
23GI0055
Fingerprint:
2125688cdc24cf…9c306de26a Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 9, 2023 (3 yrs 8 mo ago) · Target/actual end Apr 4, 2023
Description:
PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - ILOILO - CAPIZ RD (PAVIA DIVERSION) K0009 + 875 - K0010 + 816
Category:
Roads
Implementing office:
DPWH Iloilo 4th DEO · Region VI
Contractor:
IBC INTERNATIONAL BUILDERS CORPORATION · DPWH contractor code 8576
Contract amount:
₱15,678,866.75 (₱15.7M)
Funding source:
Regular Infra - GAA 2023 OO-1
Budget year:
2023
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| fbcd7874d095… | Feb 27, 2023 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ILOILO 4TH DEO | ₱15,589,969.10 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25GI0085 | Sep 9, 2025 | CONSTRUCTION OF SCHOOL BUILDING, SINAMAY ELEMENTARY SCHOOL, BARANGAY SINAMAY, ALIMODIAN, ILOILO | On-Going | ₱9.9M |
| 25GI0087 | Sep 9, 2025 | CONSTRUCTION OF SCHOOL BUILDING, ALIMODIAN NATIONAL COMPREHENSIVE HIGH SCHOOL, ALIMODIAN, ILOILO | On-Going | ₱24.6M |
| 25GI0053 | May 20, 2025 | CONSTRUCTION OF ROAD, BARANGAY QUINASPAN, ALIMODIAN, ILOILO | Completed | ₱9.8M |
| 25GI0060 | May 20, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY LAYLAYAN, ALIMODIAN, ILOILO | On-Going | ₱4.9M |
| 25GI0061 | May 20, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BANCAL ELEMENTARY SCHOOL, ALIMODIAN, ILOILO | Completed | ₱4.9M |
| 25GI0063 | May 20, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, SITIO KANANGHAN, BARANGAY BUGA, LEON, ILOILO | Completed | ₱4.9M |
| 25GI0040 | Mar 25, 2025 | OFF-CARRIAGEWAY IMPROVEMENT: PAVING OF SHOULDERS - MANDURRIAO-SN MIGUEL- ALIMODIAN-MAASIN-CABATUAN RD - K0023 + 089 - K0023 + 860 | Completed | ₱34.6M |
| 25GI0064 | Mar 11, 2025 | CONSTRUCTION OF AGANAN FLOOD CONTROL STRUCTURE, JARO-AGANAN RIVER, BARANGAY POBLACION, ALIMODIAN, ILOILO | Completed | ₱45.1M |