Project 23GL0091
DPWH infrastructure contract
Contract ID:
23GL0091
Fingerprint:
00f2de07fc3a82…79adb59145 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 4, 2023 (3 yrs 6 mo ago) · Target/actual end Oct 24, 2023
Description:
CONCRETING OF BRGY. GUINTUBHAN FMR, BRGY. GUINTUBHAN, ISABELA, NEGROS OCCIDENTAL
Category:
Roads
Implementing office:
DPWH Negros Occidental 2nd DEO · Negros Island Region
Contractor:
R.A.G. CORONA CONSTRUCTION AND AGGREGATES SUPPLY · DPWH contractor code 39473
Contract amount:
₱24,875,000.00 (₱24.9M)
Funding source:
Outside Infra - GAA 2023 DA FMR
Budget year:
2023
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| f76068ebde5f… | Apr 18, 2023 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - NEG. OCC. 2ND DEO | ₱24,551,623.81 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26RB0044 | Jun 24, 2026 | PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY -VALLEHERMOSO-CANLAON CITY-LA CASTELLANA RD - K0085 + 000 - K0087 + 242 | On-Going | ₱51.5M |
| 25RB0011 | Feb 26, 2026 | REPAIR/REHABILITATION OF CLASSROOMS, CAMP CLARK ES, ISABELA, NEGROS OCCIDENTAL (SCHOOL ID : 117201) | Completed | ₱7.5M |
| 25GL0041 | Jun 17, 2025 | ROAD CONCRETING AT BARANGAY SAN AGUSTIN, ISABELA, NEGROS OCCIDENTAL | Completed | ₱9.8M |
| 25GL0047 | Jun 17, 2025 | ROAD CONCRETING AT BARANGAY INOLINGAN, MOISES PADILLA, NEGROS OCCIDENTAL | On-Going | ₱10.3M |
| 25GL0092 | Jun 17, 2025 | CONSTRUCTION OF BINALBAGAN RIVER BANK SLOPE PROTECTION (DOWNSTREAM OF BINALBAGAN BAGACAY BRIDGE) ALONG HINIGARAN -ISABELA RD, LEFT BANK, STA 18+687.6 - 18+837.6, NEGROS OCCIDENTAL | On-Going | ₱99.0M |
| 25GL0093 | Jun 17, 2025 | CONSTRUCTION OF BINALBAGAN RIVER BANK SLOPE PROTECTION (DOWNSTREAM OF ALICANTE BRIDGE) ALONG JCT BAGONAWA - LA CASTELLANA - ISABELA RD, LEFT BANK, STA 30+030 - 30+180, NEGROS OCCIDENTAL | On-Going | ₱99.0M |
| 25GL0094 | Jun 17, 2025 | CONSTRUCTION OF GUINTUBHAN RIVER BANK CONCRETE SLOPE PROTECTION, BARANGAY MASABLAY, ISABELA, NEGROS OCCIDENTAL | On-Going | ₱48.2M |
| 25GL0071 | Jun 5, 2025 | CONSTRUCTION OF ROAD, BARANGAY TINONGAN TO BARANGAY SAN AGUSTIN, ISABELA, NEGROS OCCIDENTAL | Completed | ₱9.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.