Contract ID:
23GM0025
Fingerprint:
25b0caf9db29c7…ae4fc9630a Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 20, 2023 (3 yrs 8 mo ago) · Target/actual end Feb 8, 2024
Description:
CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE - DANCALAN-CANDONI-DAMUTAN VALLEY RD - K0143+700 - K0143+820, K0145+300 - K0145+500, CANDONI, NEGROS OCCIDENTAL
Category:
Roads
Implementing office:
DPWH Negros Occidental 3rd DEO · Negros Island Region
Contract amount:
₱91,675,000.00 (₱91.7M)
Funding source:
Regular Infra - GAA 2023 OO-1
Budget year:
2023
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26RC0021 | Jun 24, 2026 | RETROFITTING/ STRENGTHENING OF PERMANENT BRIDGES - KABILUKAN BR. (B00476NR) ALONG DANCALAN-CANDONI-DAMUTAN VALLEY RD | On-Going | ₱6.7M |
| 26RC0022 | Jun 24, 2026 | RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES - TOMAROG BR. (B00477NR) ALONG DANCALAN-CANDONI-DAMUTAN VALLEY RD | On-Going | ₱6.7M |
| 25RC0005 | Jul 28, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING- CONSTRUCTION OF COVERED COURT OF CENTRAL PHILIPPINE STATE UNIVERSITY, CANDONI CAMPUS, CANDONI, NEGROS OCCIDENTAL | Completed | ₱4.9M |
| 25GM0017 | Mar 25, 2025 | CONSTRUCTION OF CONCRETE ROAD - RECONSTRUCTION OF CONCRETE ROAD, PUROK MAHIDA-ITON ROAD JUNCTION TO BARANGAY AGBOY, BARANGAY PAYAUAN, CANDONI, NEGROS OCCIDENTAL | Completed | ₱12.9M |
| 25GM0018 | Mar 25, 2025 | CONSTRUCTION OF CONCRETE ROAD - RECONSTRUCTION OF CONCRETE ROAD, PUROK MAHIDA-ITON TO PUROK MABINULIGON, BARANGAY PAYAUAN, CANDONI, NEGROS OCCIDENTAL | Completed | ₱19.3M |
| 25GM0019 | Feb 20, 2025 | CONSTRUCTION OF CONCRETE ROAD - CONSTRUCTION OF BARANGAY PAYAUAN ROAD, BARANGAY PAYAUAN, CANDONI, NEGROS OCCIDENTAL | Completed | ₱11.8M |
| 25GM0028 | Feb 20, 2025 | CONSTRUCTION OF CONCRETE ROAD - CONSTRUCTION OF CANLAMAY TO AGBOY ROAD, BARANGAY CANLAMAY, ILOG, NEGROS OCCIDENTAL | Completed | ₱14.1M |
| 24GM0064 | Aug 5, 2024 | CONSTRUCTION OF FARM-TO-MILL ROAD, BRGY. PINGGOT, ILOG TO SITIO COGON, BRGY. GATUSLAO, CANDONI, NEGROS OCCIDENTAL | Completed | ₱16.7M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.