Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 23HC0103

DPWH infrastructure contract
Contract ID:
23HC0103
Fingerprint:
57a0dbefe1563e…fdfdc2f0a0 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 14, 2023 (3 yrs 5 mo ago) · Target/actual end Dec 24, 2023
Description:
CONCRETING OF BRGY. CAMPAMANOG FMR, BRGY. CAMPAMANOG, CARLOS P. GARCIA, BOHOL
Category:
Roads
Implementing office:
DPWH Bohol 2nd DEO · Region VII
Contractor:
EC SOLICON BUILDERS & SUPPLY, INC. · DPWH contractor code 37545
Contract amount:
₱12,735,000.00 (₱12.7M)
Funding source:
Outside Infra - GAA 2023 DA FMR
Budget year:
2023

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
88253b69391e…May 30, 2023DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BOHOL 2ND DEO₱12,735,000.00

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25HC0093Jun 5, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, PRESIDENT CARLOS P. GARCIA, BOHOLCompleted₱4.8M
24H00134Oct 18, 2024CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDING/FACILITIES, CONSTRUCTION OF STORM SURGE PROTECTION STRUCTURE AT BARANGAY PITOGO, CARLOS P. GARCIA, BOHOLOn-Going₱197.6M
24HC0161Oct 15, 2024CONSTRUCTION OF MULTI-PURPOSE BUILDING (MUNICIPAL HALL), CARLOS P. GARCIA, BOHOL (PHASE 2)Completed₱9.9M
24HC0146Oct 10, 2024CONSTRUCTION OF MULTI-PURPOSE BUILDING (MUNICIPAL HALL), CARLOS P. GARCIA, BOHOL (PHASE 3)Completed₱19.8M
24HC0162Oct 10, 2024CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDINGS, PRES. CARLOS P. GARCIA, BOHOLCompleted₱9.9M
24HC0129Oct 7, 2024REHABILITATION OF MULTI-PURPOSE BUILDINGS, CARLOS P. GARCIA, BOHOLCompleted₱19.5M
24HC0111Sep 9, 2024CONSTRUCTION OF MULTI-PURPOSE BUILDING (NEW MUNICIPAL HALL), CARLOS P. GARCIA, BOHOL (PHASE I)Completed₱29.7M
24HC0102Jul 15, 2024SUSTAINABLE INFRASTRUCTURE PROJECT ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES. CONSTRUCTION OF TUGAS SEAWALL, PRES. CARLOS P. GARCIA, BOHOLOn-Going₱144.7M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.