Project 23HD0049
DPWH infrastructure contract
Contract ID:
23HD0049
Fingerprint:
0dfda1d31a2878…a342162bc7 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 14, 2023 (3 yrs 9 mo ago) · Target/actual end Dec 8, 2023
Description:
ROAD WIDENING ALONG ANTONIO Y DE PIO H-WAY - K0113 + 017 - K0113 + 306, K0119 + 728 - K0119 + 821, K0119 + 852 - K0120 + 683, K0120 + 730 - K0120 + 916, K0134 + 585 - K0135 + 000, K0135 + 094 - K0136 + 003, TABUELAN AND SAN REMIGIO, CEBU
Category:
Roads
Implementing office:
DPWH Cebu 4th DEO · Region VII
Contractor:
DUROS DEVELOPMENT CORP. · DPWH contractor code 22729
Contract amount:
₱88,947,910.00 (₱88.9M)
Funding source:
Regular Infra - GAA 2023 OO-1
Budget year:
2023
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25HG0080 | May 19, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING OF BRGY. BUSOGON, SAN REMIGIO, CEBU | Completed | ₱4.8M |
| 25HG0092 | May 19, 2025 | IMPROVEMENT OF ROAD LEADING TO LAPYAHAN SA SAN REMIGIO, BRGY. POBLACION, SAN REMIGIO, CEBU | On-Going | ₱48.0M |
| 25HG0093 | May 19, 2025 | CONSTRUCTION OF ROAD, PUROK MAHIGUGMA-ON, BRGY. LAMBUSAN, SAN REMIGIO, CEBU | Completed | ₱9.7M |
| 25H00043 | Apr 16, 2025 | OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF SHORELINE PROTECTION STRUCTURE (PACKAGE 1) AT SAN REMIGIO, CEBU | On-Going | ₱96.5M |
| 25H00010 | Apr 11, 2025 | ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS, CEBU NORTH HAGNAYA WHARF RD - K0098 + 829 - K0099 + 889, K0102 + 000 - K0102 + 680, K0105 + 658 - K0105 + 993 | On-Going | ₱158.8M |
| 25HG0074 | Mar 27, 2025 | CONCRETING OF BRGY. SAB-A TO BRGY. LIBAONG FMR (PHASE II) WITH BOX CULVERT, BRGY. SAB-A LIBAONG, SAN REMIGIO, CEBU | Completed | ₱14.5M |
| 25HG0050 | Mar 24, 2025 | CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP), BRGY. DAPDAP-BRGY. BANCASAN-BRGY. ANAPOG-BRGY. TAMBONGON ROAD LEADING TO BEACH RESORTS AND MARINE SANCTUARIES, SAN REMIGIO, CE | Completed | ₱14.1M |
| 25HG0006 | Feb 27, 2025 | SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF ROAD, BARANGAY LAWIS TO BARANGAY MANO, SAN REMIGIO, CEBU | Completed | ₱93.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.