Project 23HJ0079
DPWH infrastructure contract
Contract ID:
23HJ0079
Fingerprint:
d03735d0d8b998…fc5cc53316 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Sep 29, 2023 (3 yrs 1 mo ago) · Target/actual end Aug 25, 2025
Description:
CONSTRUCTION OF WATER SUPPLY SYSTEMS-CONSTRUCTION OF SOLAR WATER SYSTEM, MUNICIPALITY OF MANJUYOD, NEGROS ORIENTAL
Category:
Water Provision and Storage
Implementing office:
DPWH Negros Oriental 1st DEO · Negros Island Region
Contractor:
NAKKA CONSTRUCTION · DPWH contractor code 20448
Contract amount:
₱9,746,997.99 (₱9.7M)
Funding source:
Regular Infra - GAA 2023 CSSP
Budget year:
2023
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 6dc65d0bb291… | Sep 15, 2023 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - NEGROS ORIENTAL 1S | ₱9,746,997.99 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25HJ0035 | Mar 27, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY BAGTIC, MANJUYOD, NEGROS ORIENTAL | Completed | ₱2.0M |
| 25HJ0038 | Mar 27, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY LAMOGONG, MANJUYOD, NEGROS ORIENTAL | Completed | ₱2.0M |
| 25HJ0134 | Mar 27, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-IMPROVEMENT OF CANDABONG-CABCABAN ROAD CONNEC | Completed | ₱19.6M |
| 25HJ0146 | Mar 27, 2025 | ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-PRIMARY ROAD-DUMAGUETE NORTH RD (JCT BAIS-KABANKALAN-NEGROS OCC BDRY) - K0051 + (-343) - K0051 + 765, K0051 + 790 - K0052 + 650, MANJUYOD, NEGROS ORIENTAL | Completed | ₱70.4M |
| 25HJ0165 | Mar 27, 2025 | CONSTRUCTION OF EIGHT (8) UNITS RAINWATER COLLECTOR SYSTEM (RWCS) AT NEGROS ORIENTAL 1ST DISTRICT | Completed | ₱2.6M |
| 25HJ0019 | Mar 7, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY BUTONG, MANJUYOD, NEGROS ORIENTAL | Completed | ₱2.0M |
| 25HJ0020 | Mar 7, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY CAMPUYO, MANJUYOD, NEGROS ORIENTAL | Completed | ₱2.0M |
| 25HJ0055 | Mar 7, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY PANCIAO, MANJUYOD, NEGROS ORIENTAL | Completed | ₱2.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.