Project 23ID0032
DPWH infrastructure contract
Contract ID:
23ID0032
Fingerprint:
e6804a3c663b7b…cdc8712302 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 13, 2023 (3 yrs 8 mo ago) · Target/actual end Feb 24, 2024
Description:
CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF DAGUITAN FLOOD CONTROL STRUCTURE AND DRAINAGE SYSTEM,DAGUITAN RIVER BASIN (DOWNSTREAM),BURAUEN,LEYTE
Category:
Flood Control and Drainage
Implementing office:
DPWH Leyte 2nd DEO · Region VIII
Contractor:
LANOY CONSTRUCTION · DPWH contractor code 35289
Contract amount:
₱55,280,408.90 (₱55.3M)
Funding source:
Regular Infra - GAA 2023 OO-2
Budget year:
2023
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 9e2e98a4cf2f… | Feb 27, 2023 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - LEYTE 2ND DEO | ₱54,778,017.17 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26ID0017 | Aug 27, 2026 | ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-TERTIARY ROADS, DULAG-JULITA-BURAUEN ROAD -K0952+284.00 -K0952 + 800.00, BURAUEN, LEYTE | On-Going | ₱17.2M |
| 24I00394 | Aug 7, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (DORMITORY) - EASTERN VISAYAS STATE UNIVERSITY | On-Going | ₱39.8M |
| 25ID0056 | Apr 25, 2025 | NETWORK DEVELOPMENT PROGRAM- CONSTRUCTION OF MISSING LINKS/NEW ROADS BURAUEN-ALBUERA ROAD (BURAUEN SIDE), BURAUEN,LEYTE | On-Going | ₱45.5M |
| 25ID0067 | Apr 15, 2025 | NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-BURAUEN BY PASS ROAD,LEYTE,BURAUEN,LEYTE | Completed | ₱44.8M |
| 25IF0064 | Mar 27, 2025 | CONSTRUCTION OF MISSING LINKS/NEW ROADS, ALBUERA-BURAUEN ROAD(ALBUERA SECTION), PACKAGE 8, ALBUERA, LEYTE | Completed | ₱96.2M |
| 25ID0002 | Mar 26, 2025 | ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-TERTIARY ROADS-BURAUEN-MAHAGNAO RD.-K0986+000-K0988+225.00,BURAUEN,LEYTE | Completed | ₱19.4M |
| 25ID0050 | Mar 21, 2025 | REPLACEMENT OF PERMANENT WEAK BRIDGES-MARABONG BR. (B00083LT) ALONG JARO-DAGAMI-BURAUEN-LA PAZ ROAD,BRGY. MOGUING,BURAUEN,LEYTE | Completed | ₱24.1M |
| 25IF0007 | Mar 3, 2025 | CONSTRUCTION OF BURAUEN-ALBUERA ROAD, STA. 10+580 - STA. 10+700, ALBUERA, LEYTE | Completed | ₱144.6M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.