DPWH infrastructure contract
Contract ID:
23KC0142
Fingerprint:
5b99d0d6535083…725f013069 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Dec 21, 2023 (2 yrs 10 mo ago) · Target/actual end Apr 17, 2024
Description:
CONSTRUCTION OF PUBLIC WATER SUPPLY SYSTEM LEVEL II IN BARANGAY OCCASION, SUMILAO, BUKIDNON
Category:
Water Provision and Storage
Implementing office:
DPWH Bukidnon 3rd DEO · Region X
Contractor:
RAMTRADE CONSTRUCTION AND SUPPLY · DPWH contractor code 35246
Contract amount:
₱4,825,000.00 (₱4.8M)
Funding source:
Outside Infra - Unprogrammed Appropriations 2023
Budget year:
2023
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 4c0bca1de98e… | Dec 11, 2023 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BUKIDNON 3RD DEO | ₱4,796,943.04 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25K00007 | Feb 17, 2025 | CONST. OF BY-PASS AND DIVERSION ROADS, JCT. SAYRE HIGHWAY DALIRIG - KISOLON BYPASS ROAD, PACKAGE 10, BUKIDNON | On-Going | ₱47.2M |
| 24K00409 | Nov 14, 2024 | CONSTRUCTION OF JCT. SAYRE HIGHWAY DALIRIG - KISOLON BYPASS ROAD, BUKIDNON, PACKAGE 11 | On-Going | ₱179.4M |
| 24K00435 | Aug 12, 2024 | CONST. OF BY-PASS AND DIVERSION ROADS, JCT. SAYRE HIGHWAY DALIRIG-KISOLON BYPASS ROAD, PACKAGE 11, BUKIDNON | On-Going | ₱75.6M |
| 24KC0111 | May 22, 2024 | CONSTRUCTION OF WATER SUPPLY AND RAINWATER COLLECTOR SYSTEM (RWCS), SUMILAO, BAUNGON & TALAKAG, BUKIDNON | Completed | ₱2.9M |
| 24KC0059 | Mar 14, 2024 | CONSTRUCTION OF WATER SYSTEM PUNTIAN, SUMILAO, BUKIDNON | Completed | ₱5.0M |
| 24KC0048 | Mar 8, 2024 | CONSTRUCTION OF MULTI-PURPOSE BUILDING BARANGAY PUNTIAN, SUMILAO, BUKIDNON | Completed | ₱5.0M |
| 24KC0049 | Mar 8, 2024 | CONSTRUCTION OF MULTI-PURPOSE BUILDING BARANGAY OCASION, SUMILAO, BUKIDNON | Completed | ₱5.0M |
| 24KC0050 | Mar 8, 2024 | CONSTRUCTION OF MULTI-PURPOSE BUILDING BARANGAY SAN ROQUE, SUMILAO, BUKIDNON | Completed | ₱5.0M |