Project 23KK0102
DPWH infrastructure contract
This contract as an OC4IDS project record, the infrastructure standard used by OpenGovChain. Download: JSON
{
"id": "oc4ids-pisoscan-dpwh-23KK0102",
"title": "REHABILITATION OF TOTALLY-DAMAGED CONCRETE SPILLWAY TO ODIONGAN BRIDGE 2 AND APPROACHES, GINGOOG CITY, MISAMIS ORIENTAL (PHASE II)",
"sector": [
"Bridges: Construction - Concrete (Superstructure) - with Driven Piles, Flood Control: Construction - Slope Protection using Structural Measures (e.g., Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry)"
],
"status": "completed",
"publicAuthority": {
"name": "DPWH Misamis Oriental 1st DEO"
},
"period": {
"startDate": "2023-05-08",
"endDate": "2024-06-12"
},
"budget": {
"amount": {
"amount": 96500000,
"currency": "PHP"
}
},
"locations": [
{
"geometry": {
"type": "Point",
"coordinates": [
125.20396,
8.78614
]
}
}
],
"parties": [
{
"name": "LCTING CONSTRUCTION AND DEVELOPMENT CORPORATION (FORMERLY: L.C. TING CONSTRUCTION)",
"roles": [
"supplier"
]
}
],
"contractingProcesses": [
{
"id": "23KK0102",
"summary": {
"title": "REHABILITATION OF TOTALLY-DAMAGED CONCRETE SPILLWAY TO ODIONGAN BRIDGE 2 AND APPROACHES, GINGOOG CITY, MISAMIS ORIENTAL (PHASE II)",
"status": "closed",
"contractValue": {
"amount": 96500000,
"currency": "PHP"
}
}
}
],
"pisoscan": {
"dpwhStatus": "Completed",
"physicalProgressPercent": 100,
"fundingSource": "Regular Infra - Bridges: Construction - Concrete (Superstructure) - with Driven Piles, Flood Control: Construction - Slope Protection using Structural Measures (e.g., Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry)",
"sourceDataset": "DPWH contract list via BetterGov.ph",
"sha256": "c4547c5ca6cd1a13a1b1e4dd4b26e158c6b290e661dce1703dfb7f77a2c461a5"
}
}