Project 23L00053
DPWH infrastructure contract
Contract ID:
23L00053
Fingerprint:
60c71714dabf20…467ec261cc Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 20, 2023 (3 yrs 7 mo ago) · Target/actual end Dec 10, 2023
Description:
CONSTRUCTION OF REVETMENT ALONG PADADA - MAINIT RIVER (TANWALANG SECTION) PACKAGE A, SULOP, DAVAO DEL SUR
Category:
Flood Control and Drainage
Implementing office:
DPWH Region XI · Region XI
Contractor:
ROSBILL CONSTRUCTION AND SUPPLY · DPWH contractor code 45622
Contract amount:
₱91,490,150.40 (₱91.5M)
Funding source:
Regular Infra - GAA 2023 OO-2
Budget year:
2023
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 603d9c613531… | Mar 9, 2023 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - REGION XI | ₱90,299,871.36 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26LD0001 | Jun 30, 2026 | CONSTRUCTION OF CONCRETE ROAD-ACCESS ROAD FROM WATERFALL ROAD LEADING TO PANDONG BATO TRAIL, STA. 1+700.00- STA. 1+850.00, KIBLAWAN, DAVAO DEL SUR | On-Going | ₱4.1M |
| 26LD0014 | Jun 30, 2026 | CONSTRUCTION OF CONCRETE ROAD-ACCESS ROAD LEADING TO PULA TANA VIEWING DECK, STA. 2+502.83-STA. 2+741.30, KIBLAWAN, DAVAO DEL SUR | On-Going | ₱4.2M |
| 25LD0053 | Jun 3, 2025 | CONSTRUCTION OF WATER SUPPLY SYSTEM- LEVEL II, BARANGAY KIMLAWIS, KIBLAWAN, DAVAO DEL SUR | Completed | ₱4.9M |
| 25L00080 | Apr 10, 2025 | ROAD WIDENING - BYPASS ROAD, JCT. PADADA (ALONG DIGOS - MAKAR ROAD) - KIBLAWAN - JCT. MALUNGON (ALONG DIGOS - MAKAR ROAD), PACKAGE I, DAVAO DEL SUR | On-Going | ₱86.2M |
| 25LD0124 | Mar 26, 2025 | CONSTRUCTION OF FLOOD MITIGATING STRUCTURE WITH STEEL SHEET PILE ALONG PADADA MAINIT RIVER (MASALAM BRIDGE-LAPULABAO SECTION0, HAGONOY, DAVAO DEL SUR | On-Going | ₱95.5M |
| 25LD0089 | Mar 24, 2025 | CONSTRUCTION OF MPB, BRGY. LATIAN, KIBLAWAN, DAVAO DEL SUR | Completed | ₱4.8M |
| 25LD0098 | Mar 24, 2025 | CONSTRUCTION OF MPB, BRGY. COGON, BACACA, KIBLAWAN, DAVAO DEL DUR | Completed | ₱4.8M |
| 25LD0104 | Mar 24, 2025 | CONSTRUCTION OF MPB, BRGY. SAN PEDRO, KIBLAWAN, DAVAO DEL SUR | Completed | ₱4.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.