Project 23LD0128
DPWH infrastructure contract
Contract ID:
23LD0128
Fingerprint:
c7d10fa30ec6e1…b21fe9c7ad Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 16, 2024 (2 yrs 3 mo ago) · Target/actual end Sep 20, 2024
Description:
CONCRETING OF FMR IN JUANATION SITIO CURVADA TO BRGY. LATI-AN, BRGY. LATI-AN, KIBLAWAN, DAVAO DEL SUR
Category:
Roads
Implementing office:
DPWH Davao del Sur DEO · Region XI
Contractor:
UP SCALE BUILDERS AND SUPPLY CORP. · DPWH contractor code 48939
Contract amount:
₱29,850,000.00 (₱29.9M)
Funding source:
Outside Infra - Trust Funds 2023
Budget year:
2023
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 7bf9e495b97d… | Jul 4, 2024 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - DAVAO DEL SUR DIST | ₱27,954,499.96 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26LD0001 | Jun 30, 2026 | CONSTRUCTION OF CONCRETE ROAD-ACCESS ROAD FROM WATERFALL ROAD LEADING TO PANDONG BATO TRAIL, STA. 1+700.00- STA. 1+850.00, KIBLAWAN, DAVAO DEL SUR | On-Going | ₱4.1M |
| 26LD0014 | Jun 30, 2026 | CONSTRUCTION OF CONCRETE ROAD-ACCESS ROAD LEADING TO PULA TANA VIEWING DECK, STA. 2+502.83-STA. 2+741.30, KIBLAWAN, DAVAO DEL SUR | On-Going | ₱4.2M |
| 25LD0053 | Jun 3, 2025 | CONSTRUCTION OF WATER SUPPLY SYSTEM- LEVEL II, BARANGAY KIMLAWIS, KIBLAWAN, DAVAO DEL SUR | Completed | ₱4.9M |
| 25L00080 | Apr 10, 2025 | ROAD WIDENING - BYPASS ROAD, JCT. PADADA (ALONG DIGOS - MAKAR ROAD) - KIBLAWAN - JCT. MALUNGON (ALONG DIGOS - MAKAR ROAD), PACKAGE I, DAVAO DEL SUR | On-Going | ₱86.2M |
| 25LD0124 | Mar 26, 2025 | CONSTRUCTION OF FLOOD MITIGATING STRUCTURE WITH STEEL SHEET PILE ALONG PADADA MAINIT RIVER (MASALAM BRIDGE-LAPULABAO SECTION0, HAGONOY, DAVAO DEL SUR | On-Going | ₱95.5M |
| 25LD0089 | Mar 24, 2025 | CONSTRUCTION OF MPB, BRGY. LATIAN, KIBLAWAN, DAVAO DEL SUR | Completed | ₱4.8M |
| 25LD0098 | Mar 24, 2025 | CONSTRUCTION OF MPB, BRGY. COGON, BACACA, KIBLAWAN, DAVAO DEL DUR | Completed | ₱4.8M |
| 25LD0104 | Mar 24, 2025 | CONSTRUCTION OF MPB, BRGY. SAN PEDRO, KIBLAWAN, DAVAO DEL SUR | Completed | ₱4.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.