Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 23MD0057

DPWH infrastructure contract
Contract ID:
23MD0057
Fingerprint:
198a51d1503283…65215daca5 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 24, 2023 (3 yrs 7 mo ago) · Target/actual end Nov 10, 2023
Description:
CONSTRUCTION OF CONCRETE ROAD - KIMARAYAG - NORTH COTABATO ACADEMY - SITIO TINAGO LEADING TO TINAGO FALLS, KIMARAYAG, PIGCAWAYAN, NORTH COTABATO
Category:
Flood Control: Construction - Slope Protection using Structural Measures (e.g., Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry), Roads: Construction - Gravel
Implementing office:
DPWH Cotabato 1st DEO · Region XII
Contractor:
Contract amount:
₱95,052,499.94 (₱95.1M)
Funding source:
Regular Infra - Flood Control: Construction - Slope Protection using Structural Measures (e.g., Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry), Roads: Construction - Gravel
Budget year:
2023

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25MD0073Sep 8, 2025CONSTRUCTION OF SCHOOL BUILDING, MALENGEN ELEMENTARY SCHOOL, BARANGAY MALENGEN, LIBUNGAN, COTABATOCompleted₱4.9M
25MD0060Jun 5, 2025CONSTRUCTION OF LATERAL A2 SERVICE ROAD ALONG CABPANGI ROAD, LIBUNGAN, COTABATOCompleted₱6.7M
25MD0058Apr 15, 2025LAWILI-PALACAT-BAO ROAD IN SUPPORT OF BANANA, CORN, COCONUT, AND PALM OIL INDUSTRIES, ALAMADA-ALEOSAN, NORTH COTABATOCompleted₱46.8M
25MD0022Mar 7, 2025INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES (GUARDRAILS, ROAD SIGNS, PAVEMENT MARKINGS, ROADWAY LIGHTING) ALONG BANISILAN-GUILING-ALAMADA-LIBUNGAN RD, LIBUNGAN, NORTH COTABATOCompleted₱46.8M
25MD0004Mar 6, 2025CONSTRUCTION OF PUROK 3 - PUROK 4 - PUROK 5, ROAD, BARANGAY CABPANGI, LIBUNGAN, NORTH COTABATOCompleted₱4.9M
25MD0023Mar 6, 2025CONSTRUCTION OF ROAD, DEMAPACO - SITIO MISULO, BARANGAY DEMAPACO, LIBUNGAN, NORTH COTABATOCompleted₱4.9M
24M00275Jan 15, 2025COMPLETION OF GENERAL ACADEMIC BUILDING, LIBUNGAN CAMPUS-UNIVERSITY OF SOUTHERN MINDANAO, LIBUNGAN, NORTH COTABATOOn-Going₱19.8M
24MD0050Aug 30, 2024CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG LIBUNGAN RIVER (UPSTREAM AND DOWNSTREAM OF GREBONA BRIDGE-GREBONA SECTION), BARANGAY GREBONA, LIBUNGAN, NORTH COTABATOCompleted₱96.3M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.