Project 23MH0087
DPWH infrastructure contract
Contract ID:
23MH0087
Fingerprint:
4307b6c0ca0e47…1be91f6dac Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 11, 2023 (3 yrs 7 mo ago) · Target/actual end Oct 2, 2023
Description:
REHABILITATION OF MULTIPURPOSE BUILDING, GAPOK NATIONAL HIGH SCHOOL, BRGY. GAPOK, SENATOR NINOY AQUINO, SULTAN KUDARAT
Category:
Buildings and Facilities
Implementing office:
DPWH Sultan Kudarat 2nd DEO · Region XII
Contractor:
BULLDOG ENGINEERING · DPWH contractor code 52552
Contract amount:
₱2,834,113.80 (₱2.8M)
Funding source:
Regular Infra - GAA 2023 CSSP
Budget year:
2023
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 1d0ec5b9999a… | Mar 29, 2023 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - SULTAN KUDARAT 2ND | ₱2,576,478.06 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26MH0012 | May 20, 2026 | CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE - SNA-LEBAK-KALAMANSIG RD - K1864+030 - K1864+112 | On-Going | ₱16.2M |
| 25MH0115 | Nov 12, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (GYMNASIUM), KULAMAN CENTRAL ELEMENTARY SCHOOL, BARANGAY KULAMAN, SEN. NINOY AQUINO, SULTAN KUDARAT | Completed | ₱2.3M |
| 25MH0129 | Aug 19, 2025 | CONSTRUCTION OF SCHOOL BUILDING, KUDEN NATIONAL HIGH SCHOOL, BRGY. KUDEN, SEN. NINOY AQUINO, SULTAN KUDARAT | Completed | ₱9.9M |
| 25MH0032 | Mar 25, 2025 | CONSTRUCTION OF CONCRETE ROAD - NRJ TO SITIO SEWAL LEADING TO LAGBASAN CAVE PASSING THRU BURIAL CAVE, BRGY. KUDEN, SEN. NINOY AQUINO, SULTAN KUDARAT | Completed | ₱9.5M |
| 25MH0101 | Mar 25, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY KULAMAN, SEN. NINOY AQUINO, SULTAN KUDARAT | Completed | ₱8.1M |
| 25MH0096 | Mar 21, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BUGSO, SEN. NINOY AQUINO, SULTAN KUDARAT | Completed | ₱4.8M |
| 25MH0102 | Mar 21, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (GYMNASIUM), BARANGAY LAGUBANG, SENATOR NINOY AQUINO, SULTAN KUDARAT | Completed | ₱2.2M |
| 25MH0098 | Mar 19, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY KAPATAGAN, SENATOR NINOY AQUINO, SULTAN KUDARAT | Completed | ₱2.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.