Project 23N00019
DPWH infrastructure contract
Contract ID:
23N00019
Fingerprint:
ed78f46131b7c3…b82c3f1136 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 24, 2023 (3 yrs 6 mo ago) · Target/actual end Jun 6, 2024
Description:
CONSTRUCTION OF UNION FLOOD CONTROL, BARANGAY UNION, MADRID, SURIGAO DEL SUR
Category:
Flood Control and Drainage
Implementing office:
DPWH Region XIII · Region XIII
Contractor:
LCTING CONSTRUCTION AND DEVELOPMENT CORPORATION (FORMERLY: L.C. TING CONSTRUCTION) · DPWH contractor code 23666
Contract amount:
₱109,044,970.04 (₱109.0M)
Funding source:
Regular Infra - GAA 2023 OO-2
Budget year:
2023
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 9ae673870802… | Mar 15, 2023 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - REGION XIII (CARAG | ₱107,881,475.00 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25NH0082 | Jul 25, 2025 | REHABILITATION OF ROAD, BRGY. SAN JUAN, MADRID, SURIGAO DEL SUR | Completed | ₱29.0M |
| 25N00251 | Jul 18, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BARANGAY SAN ANTONIO, MADRID, SURIGAO DEL SUR | On-Going | ₱238.1M |
| 25NH0087 | May 30, 2025 | CONSTRUCTION OF ROAD, BRGY. SAN JUAN, MADRID, SURIGAO DEL SUR | Completed | ₱4.8M |
| 25NH0065 | Apr 11, 2025 | CONSTRUCTION OF ROAD, BARANGAY SONGKIT, MADRID, SURIGAO DEL SUR | Completed | ₱19.5M |
| 25NH0032 | Feb 24, 2025 | CONSTRUCTION OF ROAD, BARANGAY LINIBUNAN, MADRID, SURIGAO DEL SUR | Completed | ₱13.8M |
| 25N00150 | Feb 21, 2025 | CARAC-AN PARALLEL BR. ALONG SURIGAO-DAVAO COASTAL RD | Completed | ₱46.8M |
| 24NH0125 | Jan 15, 2025 | CONST. OF ROADS AT BARANGAY SAN JUAN, MADRID, SURIGAO DEL SUR | Completed | ₱48.2M |
| 24NH0081 | Jun 3, 2024 | CONCRETING OF PUROK 2, BRGY. ESPERANZA TO SITIO BOYAKAN, BRGY. SAN VICENTE FMR, BRGY. ESPERANZA & BRGY. SAN VICENTE, CARMEN & MADRID, SURIGAO DEL SUR | Completed | ₱29.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.