Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 23NB0038

DPWH infrastructure contract
Contract ID:
23NB0038
Fingerprint:
be9298ce577880…e48a1fea29 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 22, 2023 (3 yrs 7 mo ago) · Target/actual end Sep 9, 2023
Description:
CONSTRUCTION OF PARALLEL BRIDGE - ANDANAN BR. (PARALLEL BR.) ALONG DAANG MAHARLIKA (AGUSAN-DAVAO SECT) (PHASE II), BAYUGAN CITY, AGUSAN DEL SUR
Category:
Bridges
Implementing office:
Contractor:
CM TAN CONSTRUCTION · DPWH contractor code 28087
Contract amount:
₱11,657,039.56 (₱11.7M)
Funding source:
Regular Infra - GAA 2023 OO-1
Budget year:
2023

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26NB0049Sep 9, 2026AGUSAN - MALAYBALAY RD (S00455MN) - K1290+841 - K1290+908.20, K1292+003.30 - K1292+066.80, K1292+163 - K1292+218, K1292+440 - K1292+836, ESPERANZA, AGUSAN DEL SUROn-Going₱125.0M
25NB0065Feb 4, 2026REPAIR/REHABILITATION OF CLASSROOMS, EAST BAYUGAN CES, BAYUGAN CITY, AGUSAN DEL SUROn-Going₱21.8M
25NB0071Feb 4, 2026CONSTRUCTION OF HEALTH CLINIC, SALVACION NATIONAL HIGH SCHOOL, BAYUGAN CITY, AGUSAN DEL SURCompleted₱3.6M
25NB0036Jun 23, 2025CONSTRUCTION OF BANK PROTECTION ALONG GIBONG RIVER (MAYGATASAN SECTION) DOWNSTREAM, BRGY. MAYGATASAN, BAYUGAN CITY, AGUSAN DEL SUR, BAYUGAN CITY, AGUSAN DEL SURCompleted₱29.6M
25NB0033May 19, 2025CONSTRUCTION OF BANK PROTECTION ALONG WAWA RIVER, PACKAGE 1, BARANGAY MAYGATASAN, BAYUGAN CITY, AGUSAN DEL SUR, BAYUGAN CITY, AGUSAN DEL SURCompleted₱67.9M
25N00145Apr 8, 2025LABAO BR. (B00906MN) ALONG MAHARLIKA HIGHWAY (AGUSAN-DAVAO SECT)Completed₱28.1M
25N00001Apr 2, 2025MAHARLIKA HIGHWAY (AGUSAN-DAVAO SECT)- K1267+569 - K1268+000, K1268+613 - K1269+290Completed₱37.9M
25N00002Apr 2, 2025MAHARLIKA HIGHWAY (AGUSAN-DAVAO SECT)- K1273+925 - K1274+067Completed₱5.0M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.