FY2026 GAA: ₱6.79T
PisoScan

Project 23NE0032

DPWH infrastructure contract
Contract ID:
23NE0032
Fingerprint:
4456a43fa67cd1…8140f39409 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 29, 2023 (3 yrs 7 mo ago) · Target/actual end Dec 21, 2023
Description:
OFF-CARRIAGEWAY IMPROVEMENT JCT MABINI-TUBAJON ROAD K0084+(-180) MABINI, TUBAJON, DINAGAT ISLANDS
Category:
Roads
Implementing office:
Contractor:
Contract amount:
₱9,770,331.31 (₱9.8M)
Funding source:
Regular Infra - GAA 2023 OO-1
Budget year:
2023

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26NE0083Aug 24, 2026REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS ALONG JCT. MABINI - TUBAJON RD - K0086 + 342 - K0086 + 442On-Going₱7.7M
26NE0049Jul 16, 2026NAME OF CONTRACT : CONSTRUCTION OF ROAD, (0+000 - 0+600), BARANGAY MALINAO, TUBAJON, DINAGAT ISLANDSOn-Going₱19.2M
25NE0024Apr 11, 2025REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE ALONG DINAGAT-LORETO RD - K0075+100-K0075+130, TUBAJON, DINAGAT ISLANDSCompleted₱1.9M
25NE0025Mar 6, 2025INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES (PAVEMENT MARKINGS) ALONG JCT MABINI-TUBAJON RD - K0084+(-280) - K0087+312, TUBAJON, DINAGAT ISLANDSCompleted₱5.8M
25NE0043Feb 26, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY IMELDA, TUBAJON, DINAGAT ISLANDSCompleted₱4.9M
25NE0052Feb 26, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY IMELDA, TUBAJON, DINAGAT ISLANDSOn-Going₱4.9M
25NE0053Feb 26, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY SANTA CRUZ, TUBAJON, DINAGAT ISLANDSCompleted₱4.9M
24NE0066May 14, 2024REHABILITATION OF MULTI-PURPOSE BUILDING (BARANGAY HALL) AT BARANGAY NAVARRO, TUBAJON, DINAGAT ISLANDSCompleted₱4.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.