Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 23NE0100

DPWH infrastructure contract
Contract ID:
23NE0100
Fingerprint:
fb861fb9074616…9ceb3cebaf Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Oct 3, 2023 (3 yrs 1 mo ago) · Target/actual end Jun 2, 2024
Description:
CONSTRUCTION OF 1STY2CL, MATINGBE ELEMENTARY SCHOOL, SAN JOSE, DINAGAT ISLANDS
Category:
Buildings and Facilities
Implementing office:
Contractor:
C.V CONSTRUCTION & DEVELOPMENT · DPWH contractor code 8334
As listed: C.V. CONSTRUCTION & DEVELOPMENT
Contract amount:
₱7,994,876.77 (₱8.0M)
Funding source:
Outside Infra - GAA 2023 DepEd BEFF
Budget year:
2023

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
66c995904088…Sep 11, 2023DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - DINAGAT ISLANDS DI₱7,764,749.90

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26NE0079Aug 24, 2026REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS ALONG DINAGAT-LORETO RD - K0020 + 000 - K0021 + 005.94, SAN JOSE, DINAGAT ISLANDSOn-Going₱27.9M
26NE0078Aug 4, 2026REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE ALONG DINAGAT-LORETO RD - K0019 + 900 - K0020 + 100, SAN JOSE, DINAGAT ISLANDSOn-Going₱25.4M
26NE0069Jul 21, 2026REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE ALONG JCT MAGSAYSAY-CAGDIANAO RD - K0006 + 000 - K0006 + 400, DINAGAT, ISLANDSOn-Going₱83.4M
26NE0074Jul 21, 2026OFF-CARRIAGEWAY IMPROVEMENT ALONG DINAGAT - LORETO RD - K0018 + 151, SAN JOSE, DINAGAT ISLANDSOn-Going₱9.6M
26NE0054Jul 8, 2026OFF-CARRIAGEWAY IMPROVEMENT ALONG DINAGAT - LORETO RD - K0011 + 733On-Going₱9.6M
26NE0062Jun 22, 2026CONSTRUCTION OF MUNICIPAL EXECUTIVE BUILDING, STA. CRUZ, SAN JOSE, DINAGAT ISLANDSOn-Going₱19.8M
26NE0057Jun 18, 2026COMPLETION OF MULTI-PURPOSE BUILDING, (BARANGAY HALL) BARANGAY MAHAYAHAY, SAN JOSE, DINAGAT ISLANDS, (10.006250, 125.585027)On-Going₱4.9M
25NE0069May 30, 2025CONSTRUCTION OF SHORE PROTECTION, STA. 0+100.00 - 0 +282, 0+095.96 - 0+338.22, BRGY. MATINGBE, SAN JOSE, DINAGAT ISLANDSOn-Going₱113.6M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.