Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 23NH0051

DPWH infrastructure contract
Contract ID:
23NH0051
Fingerprint:
738acc6a0c3bc2…86e1f90c62 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 17, 2023 (3 yrs 6 mo ago) · Target/actual end Feb 27, 2024
Description:
CONSTRUCTION OF FLOOD CONTROL, BARANGAY DAGOCDOC, TANDAG CITY, SURIGAO DEL SUR
Category:
GAA 2023 CSSP
Implementing office:
Contractor:
Contract amount:
₱96,499,030.26 (₱96.5M)
Funding source:
Regular Infra - GAA 2023 CSSP
Budget year:
2023

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25NH0142Jan 7, 2026CONST. OF SCHOOL CLINIC, WATSAN AND GROUP HANDWASHING FACILITY IN TANDAG PILOT ELEMENTARY SCHOOL, TANDAG CITY, SURIGAO DEL SURCompleted₱5.2M
25NH0140Dec 17, 2025REPAIR/REHABILITATION OF CLASSROOMS, BONGTUD ELEMENTARY SCHOOL (132960), BARANGAY BONGTUD, TANDAG CITY, SURIGAO DEL SURCompleted₱8.2M
25NH0119Sep 23, 2025CONSTRUCTION/IMPROVEMENT OF DRAINAGE BARANGAY TELAJE, TANDAG CITY, SURIGAO DEL SURCompleted₱39.2M
25NH0111Sep 4, 2025COMPLETION OF MULTI-PURPOSE BUILDING (COVERED COURT) BARANGAY BUENAVISTA, TANDAG CITY, SURIGAO DEL SURCompleted₱3.0M
25NH0125Jul 8, 2025CONSTRUCTION (COMPLETION) OF ADELA SERRA TY MEMORIAL HOSPITAL, TANDAG CITY, SURIGAO DEL SUROn-Going₱48.9M
25NH0114Jun 26, 2025CONSTRUCTION (COMPLETION) OF DPWH SURIGAO DEL SUR 1ST DEO BUILDING, TANDAG, SURIGAO DEL SUR, PHASE IIOn-Going₱4.0M
25NH0092Jun 25, 2025CONSTRUCTION OF MEDIAN / CENTER ISLAND ALONG SURIGAO - DAVAO COASTAL RD. K1298 + 396 - K1302 + 696, TANDAG CITY, SURIGAO DEL SURCompleted₱13.6M
25NH0086Jun 11, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, SAN ANTONIO, TANDAG CITY, SURIGAO DEL SURCompleted₱9.6M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.