Project 23NH0114
DPWH infrastructure contract
Contract ID:
23NH0114
Fingerprint:
db3885c85ea475…5905c37a28 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 3, 2024 (2 yrs 7 mo ago) · Target/actual end Nov 20, 2024
Description:
CONSTRUCTION OF SEAWALL BRGY. POBLACION (SITIO BAROBO), CORTES, SURIGAO DEL SUR
Category:
Flood Control and Drainage
Implementing office:
DPWH Surigao del Sur 1st DEO · Region XIII
Contractor:
LCTING CONSTRUCTION AND DEVELOPMENT CORPORATION (FORMERLY: L.C. TING CONSTRUCTION) · DPWH contractor code 23666
Contract amount:
₱67,549,669.18 (₱67.5M)
Funding source:
Outside Infra - Unprogrammed Appropriations 2023
Budget year:
2023
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| a9e29fee2afe… | Mar 6, 2024 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - SURIGAO DEL SUR 1S | ₱66,832,564.77 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26NH0063 | Sep 10, 2026 | SURIGAO-DAVAO COASTAL RD - K1276 + 818 - K1276 + 932, K1277 + 300 - K1277 + 428 | On-Going | ₱2.5M |
| 26NH0009 | Aug 14, 2026 | SURIGAO-DAVAO COASTAL RD - K1277 + 200 - K1278 + 560 | On-Going | ₱47.5M |
| 25NH0061 | Jun 11, 2025 | CONSTRUCTION OF BRIDGE LINKING BURGOS AND TAG-ANUNGAN BOTH OF CORTES, SURIGAO DEL SUR | Completed | ₱39.0M |
| 25NH0110 | Jun 9, 2025 | CONSTRUCTION (COMPLETION) OF SOLAR WATER SYSTEM IN MABAHIN, CORTES, SURIGAO DEL SUR | Completed | ₱3.9M |
| 25NH0067 | Jun 5, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL) BARANGAY TIGAO, CORTES, SURIGAO DEL SUR | Completed | ₱11.8M |
| 25NH0070 | Jun 2, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) BARANGAY MANLICO, CORTES, SURIGAO DEL SUR | Completed | ₱9.9M |
| 25NH0094 | May 30, 2025 | CONSTRUCTION OF ROADS AT MABAHIN, CORTES, SURIGAO DEL SUR | Completed | ₱4.8M |
| 25NH0112 | May 30, 2025 | COMPLETION OF MULTI-PURPOSE BUILDING (COVERED COURT), BRGY. TIGAO, CORTES, SURIGAO DEL SUR | Completed | ₱9.7M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.