Project 23OB0205
DPWH infrastructure contract
Contract ID:
23OB0205
Fingerprint:
8e2bba6b742e62…dfbb65569f Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 4, 2023 (3 yrs 7 mo ago) · Target/actual end Sep 18, 2023
Description:
REHABILITATION/UPGRADING OF MARIKINA POLYTECHNIC COLLEGE (ELECTRICAL POWER SYSTEM), MARIKINA CITY
Category:
Buildings and Facilities
Implementing office:
DPWH Metro Manila 1st DEO · National Capital Region
Contractor:
PRUDENT DIAMOND SQUARE CONSTRUCTION CO. · DPWH contractor code 31726
Contract amount:
₱47,505,494.40 (₱47.5M)
Funding source:
Regular Infra - GAA 2023 CSSP
Budget year:
2023
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 3c50ccdb2f46… | Mar 27, 2023 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - METRO MANILA 1ST E | ₱47,505,494.40 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25OB0459 | May 22, 2025 | RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES - MARIKINA BR. (B01866LZ) ALONG A BONIFACIO AVE | On-Going | ₱144.9M |
| 25OB0262 | May 20, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, NANGKA RIVER,MARIKINA CITY | Completed | ₱47.8M |
| 25OB0263 | May 20, 2025 | REHABILITATION OF FLOOD CONTROL STRUCTURE ALONG NANGKA RIVER, MARIKINA CITY | Completed | ₱38.1M |
| 25OB0285 | May 20, 2025 | INSTALLATION OF ROAD SAFETY DEVICES ALONG ORDONEZ STREET, SECOND DISTRICT, MARIKINA CITY | On-Going | ₱38.0M |
| 25OB0287 | May 20, 2025 | INSTALLATION OF ROAD SAFETY DEVICES ALONG F. MANALO STREET INCLUDING LATERALS, BARANGAY NANGKA, MARIKINA CITY | Completed | ₱9.5M |
| 25OB0289 | May 20, 2025 | INSTALLATION OF M. SEVILLA ROAD SAFETY DEVICES INCLUDING LATERALS, BARANGAY PARANG, MARIKINA CITY | Completed | ₱9.3M |
| 25OB0290 | May 20, 2025 | INSTALLATION OF SHOE AVENUE, AMANG RODRIGUEZ, ROAD SAFETY DEVICES, BARANGAY CONCEPCION UNO, MARIKINA CITY | Completed | ₱9.5M |
| 25OB0294 | May 20, 2025 | INSTALLATION OF ORO VISTA SUBDIVISION ROAD SAFETY DEVICES, BARANGAY CONCEPCION UNO, MARIKINA CITY | On-Going | ₱9.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.