Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 23OB0440

DPWH infrastructure contract
Contract ID:
23OB0440
Fingerprint:
083ee1774e9f42…f74e788cdf Verified
Status:
On-Going
Physical progress:
0.1%
Timeline:
Start Nov 13, 2023 (3 yrs ago)
Description:
CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING AT KOROKAN, BRGY. WESTERN BICUTAN, TAGUIG CITY
Category:
Buildings and Facilities
Implementing office:
DPWH Metro Manila 1st DEO · National Capital Region
Contractor:
HONY TRADING & CONSTRUCTION · DPWH contractor code 26898
Contract amount:
₱11,582,224.64 (₱11.6M)
Funding source:
Regular Infra - GAA 2023 CSSP
Budget year:
2023

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
3bd53d233eaa…Oct 27, 2023DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - METRO MANILA 1ST E₱11,582,224.64

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25OB0443Jul 13, 2026CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. NEW LOWER BICUTAN, TAGUIG CITY (PHASE 1)On-Going₱46.9M
25OB0367Apr 15, 2026CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING AND SITE DEVELOPMENT AT LAKESHORE AT BARANGAY LOWER BICUTAN, TAGUIG CITYOn-Going₱47.0M
25OB0409Aug 14, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, NRCPO, CAMP BAGONG DIWA, TAGUIG CITYOn-Going₱29.1M
25OB0437Aug 14, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, SPD COMPOUND, LAWTON AVE., BARANGAY WESTERN BICUTAN, TAGUIG CITY (PHASE 1)On-Going₱48.5M
25OC0178Jul 8, 2025REHABILITATION/IMPROVEMENT OF SOUTH SUPER H-WAY WEST SERVICE RD (S03387LZ)(INTERMITTENT) PARAÑAQUE CITY, METRO MANILACompleted₱12.8M
25OB0371Jun 27, 2025CONSTRUCTION OF MULTI-PURPOSE FACILITIES AT LAKESHORE, BARANGAY LOWER BICUTAN, TAGUIG CITY (PHASE 1)On-Going₱48.5M
25OB0372Jun 27, 2025CONSTRUCTION OF MULTI-PURPOSE FACILITIES AT LAKESHORE, BARANGAY LOWER BICUTAN, TAGUIG CITY (PHASE 2)On-Going₱48.5M
25OB0373Jun 27, 2025CONSTRUCTION OF MULTI-PURPOSE FACILITIES AT LAKESHORE, BARANGAY LOWER BICUTAN, TAGUIG CITY (PHASE 5)On-Going₱72.7M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.