Project 23OB0447

DPWH infrastructure contract
Contract ID:
23OB0447
Fingerprint:
3b7488574decdd…3f31f865dd Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Dec 28, 2023 (2 yrs 10 mo ago) · Target/actual end Aug 23, 2024
Description:
CONSTRUCTION OF MULTI-PURPOSE FACILITY (LINEAR PARK) ALONG TAGUIG RIVER (WEST BANK), TAGUIG CITY
Category:
Buildings and Facilities
Implementing office:
DPWH Metro Manila 1st DEO · National Capital Region
Contractor:
B. BERNARDO CONST., INC. · DPWH contractor code 6196
Contract amount:
₱75,654,717.65 (₱75.7M)
Funding source:
Regular Infra - GAA 2023 CSSP
Budget year:
2023

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
c4e869b07e51…Dec 19, 2023DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - METRO MANILA 1ST E₱75,654,717.65

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25OB0443Jul 13, 2026CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. NEW LOWER BICUTAN, TAGUIG CITY (PHASE 1)On-Going₱46.9M
25OB0367Apr 15, 2026CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING AND SITE DEVELOPMENT AT LAKESHORE AT BARANGAY LOWER BICUTAN, TAGUIG CITYOn-Going₱47.0M
25OB0409Aug 14, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, NRCPO, CAMP BAGONG DIWA, TAGUIG CITYOn-Going₱29.1M
25OB0437Aug 14, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, SPD COMPOUND, LAWTON AVE., BARANGAY WESTERN BICUTAN, TAGUIG CITY (PHASE 1)On-Going₱48.5M
25OC0178Jul 8, 2025REHABILITATION/IMPROVEMENT OF SOUTH SUPER H-WAY WEST SERVICE RD (S03387LZ)(INTERMITTENT) PARAÑAQUE CITY, METRO MANILACompleted₱12.8M
25OB0371Jun 27, 2025CONSTRUCTION OF MULTI-PURPOSE FACILITIES AT LAKESHORE, BARANGAY LOWER BICUTAN, TAGUIG CITY (PHASE 1)On-Going₱48.5M
25OB0372Jun 27, 2025CONSTRUCTION OF MULTI-PURPOSE FACILITIES AT LAKESHORE, BARANGAY LOWER BICUTAN, TAGUIG CITY (PHASE 2)On-Going₱48.5M
25OB0373Jun 27, 2025CONSTRUCTION OF MULTI-PURPOSE FACILITIES AT LAKESHORE, BARANGAY LOWER BICUTAN, TAGUIG CITY (PHASE 5)On-Going₱72.7M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.