Project 23OI0032
DPWH infrastructure contract
Contract ID:
23OI0032
Fingerprint:
59bd2a98aa1877…baf9522d37 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Aug 22, 2023 (3 yrs 2 mo ago) · Target/actual end Dec 19, 2023
Description:
CONSTRUCTION OF FLOOD CONTROL STRUCTURE, ZAPOTE RIVER, LAS PINAS CITY
Category:
Flood Control and Drainage
Implementing office:
DPWH Las Piñas-Muntinlupa DEO · National Capital Region
Contractor:
Contract amount:
₱48,993,363.57 (₱49.0M)
Funding source:
Regular Infra - GAA 2023 OO-2
Budget year:
2023
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| e390c8ee7655… | Aug 29, 2023 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - LAS PINAS- MUNTINL | ₱47,032,231.71 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25DQ0110 | Jul 3, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY MALIKSI 2, BACOOR CITY, CAVITE | On-Going | ₱9.8M |
| 25DQ0111 | Jul 3, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BAYANAN, BACOOR CITY, CAVITE | On-Going | ₱9.8M |
| 25DF0158 | Jul 1, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAMBASIC INFRASTRUCTURE PROGRAM (BIP)ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITESCONSTRUCTION OF ROAD WITH DRAINAGE AT BRGY. PALICO IV, CITY OF IMUS, | On-Going | ₱4.8M |
| 25DQ0084 | Jun 17, 2025 | CONSTRUCTION OF RIVERWALL AND OTHER IMPROVEMENT WORKS ALONG BACOOR RIVER, PHASE 1, CITY OF BACOOR, CAVITE | On-Going | ₱96.0M |
| 25DQ0085 | Jun 17, 2025 | CONSTRUCTION OF RIVERWALL AND OTHER IMPROVEMENT WORKS ALONG BACOOR RIVER, PHASE 2, CITY OF BACOOR, CAVITE | On-Going | ₱98.0M |
| 25DQ0090 | Jun 17, 2025 | CONSTRUCTION OF SLOPE AND BANKS PROTECTION WORKS ALONG BACOOR RIVER, CITY OF BACOOR, CAVITE (PHASE 1) | On-Going | ₱98.0M |
| 25DQ0099 | Jun 17, 2025 | CONSTRUCTION OF SLOPE AND BANKS PROTECTION WORKS ALONG BACOOR RIVER, CITY OF BACOOR, CAVITE (PHASE 3) | On-Going | ₱98.0M |
| 25DQ0101 | Jun 17, 2025 | CONSTRUCTION OF SLOPE AND BANKS PROTECTION WORKS ALONG BACOOR RIVER, CITY OF BACOOR, CAVITE (PHASE 2) | On-Going | ₱98.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.